Dear Shareholders,
Your Directors are pleased to present the 23rd Annual Report and Audited Financial Statements for the Financial Year ended 31st March, 2026 together with the reports of Statutory Auditors. Comments of Comptroller & Auditor General of India are yet to be received by the Company.
1. FINANCIAL PERFORMANCE HIGHLIGHTS
The key highlights of the financial performance of the company during F.Y. 2025-26 along with the corresponding performance in F.Y. 2024-25 are mentioned below (rounded to nearest rupees/crore):
|
Particulars
|
2025-26
|
2024-25
|
%
Increase/
Decrease
|
|
Turnover
|
20,012.26
|
19,869.35
|
0.72%
|
|
Total Income
|
20,818.75
|
20,888.24
|
-0.33%
|
|
Operating Income
|
1,190.60
|
1,470.29
|
-19.02%
|
|
Reserves & Surplus
|
6,777.80
|
6,538.70
|
3.66%
|
|
Profit Before Tax
|
1,102.27
|
1,550.18
|
-28.89%
|
|
Profit After Tax
|
800.48
|
1,188.62
|
-32.66%
|
|
Net worth
|
8862.824
|
8,623.72
|
2.77%
|
|
Appropriations
|
|
|
|
|
Final Dividend
|
148.04*
|
358.62
|
|
|
Interim Dividend
|
208.50
|
|
|
* Final dividend amounting to D148.04 crore @ D0.71 per fully paid equity share recommended by the Board of Directors subject to the approval of shareholders in the ensuing Annual General Meeting of the Company.
Capital Structure
With an Authorized share capital of the Company of D3000 crores, there has been no change in the Capital Structure of the Company, with the Paid-up share capital of the Company remaining at D2085.02 crore. The Company has not issued any share during the year under consideration.
Employee Stock Option Plan
Your Company has not provided any Employee Stock Option Plan (ESOP); therefore, disclosure requirement in relation to ESOP under Rule 12(9) and Rule 16(4) of the Companies (Share Capital and Debentures) Rules, 2014 is not applicable.
Shareholding of President of India (POI)
As on 31.03.2026, the present Shareholding of President of India (POI) is 1,51,87,43,694 equity shares of C10 each amounting to D 15,18,74,36,940 i.e. 72.84%.
Profit
Profit before Tax decreased from D1,550.18 crore in
2024- 25 to D1,102.27 crore in 2025-26 showing a decrease of 28.89%. Profit after Tax decreased from D1,188.62 crore in F. Y. 2024-25 to D800.48 crore in F. Y.
2025- 26 showing a decrease of 32.66%.
Net Worth
The Net Worth of your Company has increased over the previous year from D8,623.73 crore to D8,862.82 crore on
account of transfer of profits (after payment of Dividend).
Reserves
The Reserves & Surplus of the Company for FY 2025-26 stand at D6,777.80 crore as compared to D6,538.70 crore in FY 2024-25, showing an increase of 3.66% from previous year.
Dividend
The Board recommended a final dividend of D148.04 crores (C0.71 per share) subject to the approval of shareholders in the ensuing Annual General Meeting of the Company. Total dividend for the financial year 2025-26 is D356.54 crore.
Acceptance of Deposits
Your company has not accepted any deposit from the public during the year.
Reimbursement of Expenditure
RVNL received an amount of D12,509 crores (approx.) for project expenditure during the current year, from Ministry of Railways (MoR) for execution of various works.
Loans from IRFC
During the year, no borrowing was made from IRFC. With this, the total amount received from IRFC is D7865.08 crore. The principal and interest on the borrowings from IRFC are repaid by Ministry of Railways (MoR) as a pass-through entry in the books of RVNL. During the year, an amount of D499.51 crore towards principal & D570.15 crore towards interest was paid to IRFC on this account, leaving an outstanding loan& Principal balance of D5278.07 crore (including interest accrued of D1285.22 Cr).
Turnover
Your Company has achieved a turnover of D20,012.26 crore in 2025-26 as compared to D 19,869.35 crore in 2024-25.
At the same time, there has also been a significant increase in the revenue from the projects secured through
bidding to the tune of D6283.04 crore during 2025-26 in comparison to D2771.50 crore in the previous year.
Consolidated Financial Statements
The consolidated Financial Statements of the Company prepared in accordance with the provisions of Companies Act, 2013 and the applicable Indian Accounting Standards (IND-AS) for the financial year 2025-26 forms part of the Annual Report of the Company. The accounts have been consolidated with SPVs, JVs, Associates and its wholly owned subsidiaries. The related entries appearing in the standalone accounts of RVNL have been adjusted accordingly in consonance with the relevant Indian Accounting Standards (Ind AS 110& 28). The salient features of differences in the significant entries between the Standalone Accounts of RVNL and the Consolidated Accounts are as under:
|
Particular
|
Figures as on 31.3.2026 Standalone
|
Figures as on 31.3.2026 Consolidated
|
|
Turnover
|
20012.26
|
20412.12
|
|
Other Income
|
806.49
|
775.23
|
|
Direct Expenses
|
18821.66
|
19187.18
|
|
Indirect Expenses
|
894.82
|
912.81
|
|
PBT
|
1102.27
|
1181.24*
|
|
PAT
|
800.48
|
870.66
|
|
Reserve & Surplus
|
6777.80
|
7733.08
|
|
Net Worth
|
8862.82
|
9818.10
|
* PBT includes C93.88 crore as proportionate share of RVNL in the profit/loss of Joint Ventures.
Subsidiary, Joint Venture and Associate Companies
During the financial year under review, the Company has incorporated a wholly-owned subsidiary namely Sabbavaram Sheelanagar Road Development Limited.
The performance and financial position of the subsidiary companies, associates and joint venture is provided in the consolidated financial statement.
The Policy for determining material subsidiary Companies as approved by the Board may be accessed on the Company's website athttps://rvnl.org/RVNL cms/ uploads/copolicv/RVNLMaterialitvPolicies.pdf.
Integral Reports
Name of Report Annexure
Management Discussion and Analysis A
Corporate Governance Report B
Corporate Social Responsibility (CSR) C
Report
Business Responsibility and Sustainability D
Report (BRSR)
Secretarial Auditor Report E
Form AOC-2 F
The Management Discussion and Analysis Report provides an overview of the affairs of the Company, its business environment, mission and objectives, outlook, operational performance, its resources and systems, strengths, opportunities, constraints, risks and concerns, strategies, prospects, etc. (Annexure A).
The Corporate Governance Report highlights the Company's philosophy on Corporate Governance and Key Values, composition of Board of Directors and its Committees, attendance and remuneration of Directors etc. other relevant disclosures, CEO/CFO Certification and general information for shareholders. The following compliance certificates as required under DPE Guidelines and SEBI Regulations supplement it. (Annexure B).
• A Certificate signed by the Chairman and Managing Director affirming receipt of compliance with the Code of Conduct from all Board members and Senior Management personnel during the year 2025-26 (placed at Annexure “B-1") as per guidelines of Department of Public Enterprises on Corporate Governance.
• A Certificate from the Chairman and Managing Director (CMD) and Chief Financial Officer (CFO) with regard to the authenticity of financial statements (placed at Annexure “B-2"); and
• A Certificate of compliance on Corporate Governance signed by a practicing Company Secretary (placed at Annexure “B-3") as per guidelines of Department of Public Enterprises on Corporate Governance and Listing Regulations.
• Certificate on non-disqualification of Directors as per schedule V of SEBI (LODR) Regulations, 2015 (placed at Annexure “B-4")
The Corporate Social Responsibility (CSR) Report
reflects RVNL's plans, policy, budget, expenditure, evaluation process for projects and CSR activities undertaken during the year. (Annexure C)
The “Business Responsibility and Sustainability Report (BRSR)" describes the initiatives taken by the Company from an Environmental, Social and Governance (ESG) perspective in terms of amendment to Regulation 34 (2) (f) of SEBI (LODR) Regulations 2015. (Annexure D)
Pursuant to provisions of Section 204 of Companies Act, 2013, Regulation 24A of the SEBI (LODR) Regulations and Companies (Appointment and Remuneration of Managerial personnel) Rules 2014, the Company has appointed M/s. Sinha & Srivastava LLP, A firm of Company Secretaries, to undertake the Secretarial Audit of the Company. The Secretarial Audit Report is placed at Annexure “E".
As per Section 92 (3) of the Companies Act, 2013, Annual Return will be available on the website of the Company i.e., www.rvnl.org.
The disclosure of Related Party Transactions, as required under section 134 (3) (h) of Companies Act, 2013 and Rule 8 (2) of the Companies (Accounts) Rules, 2014 in Form "AOC-2" is placed at Annexure "F".
3. Operational Performance
Your Directors are delighted to inform that the F.Y. 2025-26 has been a year of operational excellence and growth for the Company.
In 2025-26, 173.82 km sections were commissioned consisting of 12.14 km of New Line and 161.68 km of Doubling handed over to Zonal Railways for operations.
During the year, Phephna-Indara, Mau-Shahganj (excluding Indara-Mau) (150.28 km) doubling project fully commissioned.
Out of 160 projects completed so far, 158 projects have been fully commissioned and handed over to Railways for operations and maintenance.
Signalling & Telecommunication:
RVNL is a major contributor in providing EI installations on Indian Railways in connection with Doubling, 3rd Line, New Line and Gauge Conversion. Keeping its tradition high, during FY 2025-26, RVNL has commissioned New Electronic Interlocking and alteration in existing Electronic Interlocking at 48 Stations on Indian Railways.
RVNL has also commissioned 7 nos. Major Yard remodeling work on Indian Railways viz. Jakhapura, Milavittan, Manoharpur, Tenali, Sambalpur, Mathura and Dhuri stations with routes varying from 200 to 600+ Routes.
Railway Electrification:
During the year, Railway Electrification of 173.82 km was commissioned as part of Doubling.
3.1 Physical Size of the Projects:
Since its establishment in 2003, Ministry of Railways has transferred 185 projects to RVNL for execution, which may be broadly classified under the following heads:
• Doubling 69
• Gauge Conversion 12
• New Lines 13
• MTP 06
• Railway Electrification 39
• Workshops 21
• Others 25
And after implementation of revocation of policy for assignment of work to PSUs in 2021, RVNL had participated in Open Bidding and projects awarded through biddings and taken Nomination work other then Railways as on March 2026 are:
• Awarded through Bidding 104
• Nomination work other then Railway Projects 10
The distribution of project length under various plan heads of Railway works is shown below:
3.1.1 Nature of Works being Executed by RVNL:
RVNL is executing all types of Railway Infrastructure works such as New Line, Gauge Conversion, Doubling/3rd Line/4th Line, Railway Electrification, Workshops, Hill Railway Projects, Institutional & Residential Buildings, Mega Bridges, Metro Railway, Port, Tunnels, Monumental Bridges, Canals, Transmission Lines, Highways, Signalling Work, MMLPs etc.
3.1.2 Project Implementation Units (PIUs):
These projects are spread all over the country and for efficient implementation of projects, 27 Project Implementation Units (PIUs) established at 23 locations to execute projects in their geographical hinterland. They are located at Ahmedabad, Agra, Bengaluru, Bhopal, Bhubaneshwar, Chennai (2 Units), Chandigarh, Indore, Kolkata (3 Units), Kharagpur, Lucknow, Mumbai, Nagpur, Patna, Pune, Raipur, Rishikesh, Ranchi, Secunderabad, Varanasi (2 Units), Delhi, Bharatnet (East-Lucknow, West-
Noida) and Waltair. The PIUs are established and closed as per requirement.
The Company has foreign presence in Maldives, Abu Dhabi, Dubai, Saudi Arabia, South Africa, Uzbekistan, Oman, Rwanda and Kyrgyzstan.
3.2 Status of physical progress of projects
The status of the 299 projects is as under: -
|
Projects commissioned up to March 2026
|
158 No.
|
|
•
|
Doubling
|
63 No.
|
|
•
|
Gauge Conversion
|
11 No.
|
|
•
|
New Lines
|
07 No.
|
|
•
|
MTP
|
02 No.
|
|
•
|
Railway Electrification
|
38 No.
|
|
•
|
Workshops
|
19 No.
|
|
•
|
Others
|
20 No.
|
|
Projects under implementation
|
141 No.
|
|
•
|
MoR :
|
27 No
|
|
•
|
Bidding Works :
|
104 No.
|
|
•
|
Nomination works other than Railways :
|
10 No.
|
RVNL has so far completed 160 projects.
The list of 160 projects fully completed up to March 2026 is as under:
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
1.
|
Central Railway
|
Diva - Kalyan 5th & 6th Line
|
Doubling
|
11
|
|
2.
|
Central Railway
|
Pakni - Mohol Doubling
|
Doubling
|
17
|
|
3.
|
Central Railway
|
Panvel - Jasai JNPT Doubling
|
Doubling
|
28.5
|
|
4.
|
Central Railway
|
Pakni - Solapur Doubling
|
Doubling
|
16.28
|
|
5.
|
Central Railway & SCR
|
Daund- Gulbarga- Doubling (224.9 km) and Pune- Guntakal -Electrification (641.37 km)
|
Doubling
|
224.9
|
|
6.
|
Eastern Railway
|
Gurup - Saktigarh Extn of 3,d Line
|
Doubling
|
26
|
|
7.
|
East Central Railway
|
Barauni - Tilrath Bypass Doubling
|
Doubling
|
8.3
|
|
8.
|
East Coast Railway
|
Talcher-Cuttack-Paradeep Doubling with 2nd Bridge on Rivers Birupa & Mahanadi
|
Doubling
|
3
|
|
9.
|
East Coast Railway
|
Jakhapura- Haridaspur 3'd Line
|
Doubling
|
23.3
|
|
10.
|
East Coast Railway
|
Cuttack - Barang Doubling
|
Doubling
|
14.3
|
|
11.
|
East Coast Railway
|
Rajatgarh-Barang Doubling
|
Doubling
|
31.3
|
|
12.
|
East Coast Railway
|
Khurda-Barang - 3rd line (35 km)
|
Doubling
|
32.32
|
|
13.
|
East Coast Railway
|
Sambalpur-Titlagarh (182 km)
|
Doubling
|
182.00
|
|
14.
|
East Coast Railway
|
Raipur-Titlagarh (203 km)
|
Doubling
|
203
|
|
15.
|
East Coast Railway
|
Banspani-Daitari-Tomka-Jakhapura (180 km)
|
Doubling
|
180
|
|
16.
|
Northern Railway
|
New Delhi-Tilak Bridge- 5th & 6th line (2.65 km)
|
Doubling
|
2.65
|
|
17.
|
Northern Railway
|
Utraitia-Raebareli (65.6 km)
|
Doubling
|
68.04
|
|
18.
|
Northern Railway
|
Raebareli-Amethi (60.1 km)
|
Doubling
|
59.00
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
19.
|
Northern Railway
|
Rajpura-Bhatinda Doubling with Electrification (172.64 km)
|
Doubling
|
172.64
|
|
20.
|
Northern Railway
|
Janghai- Phahamau DL
|
Doubling
|
49.16
|
|
21.
|
North Central Railway
|
Palwal - Bhuteswar 3rd Line
|
Doubling
|
81
|
|
22.
|
North Central Railway
|
Aligarh - Ghaziabad 3rd Line
|
Doubling
|
106.1
|
|
23.
|
North Central Railway
|
Bhimsen-Jhansi (206 km) with RE
|
Doubling
|
206
|
|
24.
|
North Eastern Railway
|
Varanasi- Madhosingh- Allahabad
|
Doubling
|
120.35
|
|
25.
|
North Eastern Railway
|
Phephna-Indara, Mau-Shahganj (excluding Indara- Mau) (150.28 km)
|
Doubling
|
150.28
|
|
26.
|
North Western Railway
|
Bhagat Ki Kothi - Luni Doubling
|
Doubling
|
30.3
|
|
27.
|
North Western Railway
|
Karjoda - Palanpur Doubling
|
Doubling
|
5.4
|
|
28.
|
North Western Railway
|
Rewari- Manheru Doubling
|
Doubling
|
69.02
|
|
29.
|
North Western Railway
|
Rani-Keshav Ganj Doubling
|
Doubling
|
59.5
|
|
30.
|
North Western Railway
|
Abu Road-Sarotra Road- Patch doubling (23.12 km)
|
Doubling
|
23.12
|
|
31.
|
North Western Railway
|
Swaruganj-Abu Road - Patch doubling (25.36 km)
|
Doubling
|
25.36
|
|
32.
|
North Western Railway
|
Sarotra Road-Karjoda - Patch doubling (23.59 km)
|
Doubling
|
23.59
|
|
33.
|
Southern Railway
|
Attipattu - Korukkupet 3,d Line
|
Doubling
|
18
|
|
34.
|
Southern Railway
|
Pattabiram - Tiruvallur 4th Line & Tiruvallur - Arakkonam 3rd Line
|
Doubling
|
41.89
|
|
35.
|
Southern Railway
|
Tiruvallur - Arakkonam 4th Line
|
Doubling
|
28
|
|
36.
|
Southern Railway
|
Villipuram-Dindigul Doubling
|
Doubling
|
273
|
|
37.
|
Southern Railway
|
Thanjavur-Ponmalai - Doubling
|
Doubling
|
46.96
|
|
38.
|
Southern Railway
|
Madurai-Maniyachi-Tuticorin (160 km)
|
Doubling
|
160
|
|
39.
|
Southern Railway
|
Maniyachi-Nagercoil DL
|
Doubling
|
102
|
|
40.
|
South Central Railway
|
Pullampet - Balapalle Ph I of Gooty - Renigunta Doubling
|
Doubling
|
41
|
|
41.
|
South Central Railway
|
Krishnapatnam - Venkatachalam Doubling with RE
|
Doubling
|
16.5
|
|
42.
|
South Central Railway
|
Gooty - Renigunta Patch Doubling
|
Doubling
|
151
|
|
43.
|
South Central Railway
|
Raichur - Guntakal Doubling
|
Doubling
|
81.0
|
|
44.
|
South Central Railway
|
Guntur-Tenali - Doubling with electrification (24.38 km)
|
Doubling
|
25
|
|
45.
|
South Central Railway
|
Vijaywada-Gudivada- Bhimavaram-Narasapur, Gudivada-Machlipatnam and Bhimavaram- Nidadavolu (221 km) - Doubling with electrification
|
Doubling
|
221.00
|
|
46.
|
South Central Railway
|
Secunderabad (Falaknuma)-Mehbubnagar doubling
|
Doubling
|
85.70
|
|
47.
|
South Central Railway
|
Vijaywada - Gudur 3rd Line Project
|
Doubling
|
287.67
|
|
48.
|
South Eastern Railway
|
Tikiapara - Santragachi Doubling
|
Doubling
|
5.6
|
|
49.
|
South Eastern Railway
|
Panskura - Kharagpur 3'd Line
|
Doubling
|
45
|
|
50.
|
South Eastern Railway
|
Panskura - Haldia Ph 1 Doubling
|
Doubling
|
14
|
|
51.
|
South Eastern Railway
|
Rajgoda - Tamluk (Jn. Cabin) Doubling
|
Doubling
|
13.5
|
|
52.
|
South Eastern Railway
|
Tamluk Jn. Cabin - Basulya Sutahata Doubling
|
Doubling
|
24.23
|
|
53.
|
South Eastern Railway
|
Goelkera-Monoharpur 3rd line (40 km)
|
Doubling
|
27.5
|
|
54.
|
South East Central Railway
|
Bilaspur - Urkura 3rd Line Doubling
|
Doubling
|
105
|
|
55.
|
South East Central Railway
|
Salka Road- Khongsara Patch Doubling
|
Doubling
|
26
|
|
56.
|
South East Central Railway
|
Khodri-Anuppur, with Flyover at Bilaspur (61.6 km)
|
Doubling
|
61.6
|
|
57.
|
South Western Railway
|
Hospet - Guntakal Doubling
|
Doubling
|
115
|
|
58.
|
West Central Railway
|
Bhopal-Bina - 3rd line (143 km)
|
Doubling
|
144.3
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
59.
|
West Central Railway
|
Itarsi-Budni - 3rd line (25.090 km)
|
Doubling
|
25.09
|
|
60.
|
West Central Railway
|
Barkhera-Habibganj - 3rd line (41.420 km)
|
Doubling
|
41.2
|
|
61.
|
West Central Railway
|
Bina-Kota (282.66 km) with RE
|
Doubling
|
282.66
|
|
62.
|
West Central Railway
|
Barkhera - Budni 3rd line
|
Doubling
|
26.5
|
|
63.
|
Western Railway
|
Palanpur- Samakhiali (247.73 km)
|
Doubling
|
247.3
|
|
64.
|
North Eastern Railway
|
Lucknow-Pilibhit via Sitapur, Lakhimpur (262.76 km)
|
GC
|
262.76
|
|
65.
|
North Western Railway
|
Delhi - Rewari Gauge Conversion
|
GC
|
94.2
|
|
66.
|
North Western Railway
|
Ajmer - Phulera - Ringus - Rewari Gauge Conversion
|
GC
|
295
|
|
67.
|
North Western Railway
|
Bhildi - Samdari Gauge Conversion
|
GC
|
223
|
|
68.
|
Southern Railway
|
Thanjavur - Villupuram Gauge Conversion
|
GC
|
192
|
|
69.
|
Southern Railway
|
Cuddalore - Salem Gauge Conversion
|
GC
|
193
|
|
70.
|
South Western Railway
|
Arasikere-Hassan-Mangalore Gauge Conversion
|
GC
|
230
|
|
71.
|
Western Railway
|
Bharuch - Samni - Dahej Gauge Conversion
|
GC
|
62
|
|
72.
|
Western Railway
|
Gandhidham - Palanpur Gauge Conversion
|
GC
|
301
|
|
73.
|
Western Railway
|
Ahmedabad-Botad (170.48 km)
|
GC
|
166.09
|
|
74.
|
Western Railway
|
Dhasa-Jetalsar (104.44 km)
|
GC
|
106.69
|
|
75.
|
East Coast Railway
|
Daitari - Banspani New Line
|
New Line
|
155
|
|
76.
|
East Coast Railway
|
Haridaspur-Paradeep (82 km)
|
New Line
|
82
|
|
77.
|
East Coast Railway
|
Angul- Sukinda Road (98.7 km)
|
New Line
|
95
|
|
78.
|
North Eastern Railway
|
Mau-Gazipur-Tarighat New Line
|
New Line
|
16.79
|
|
79.
|
Southern Railway
|
Vallarpadam - Idapally New Line
|
New Line
|
9
|
|
80.
|
South Central Railway
|
Obulavaripalle- Krishnapattnam (113 km)
|
New Line
|
121
|
|
81.
|
Railway Electrification
|
Tomka -Banspani - RE
|
RE
|
144
|
|
82.
|
Railway Electrification
|
Kharagpur (Nimpura) - Bhubaneswar Including Branch Line of Talcher - Cuttack - Paradeep
|
RE
|
581
|
|
83.
|
Railway Electrification
|
Bhubaneswar - Kottavalasa
|
RE
|
417
|
|
84.
|
Railway Electrification
|
Daund-Manmad Incl. Puntamba- Shirdi - RE
|
RE
|
255
|
|
85.
|
Railway Electrification
|
Reningunta - Guntakal RE
|
RE
|
308
|
|
86.
|
Railway Electrification
|
Yelahanka - Dharmavaram - Gooty RE
|
RE
|
306
|
|
87.
|
Railway Electrification
|
Bharuch - Samni - Dahej RE
|
RE
|
64
|
|
88.
|
Railway Electrification
|
Manheru- Hissar RE
|
RE
|
74
|
|
89.
|
Railway Electrification
|
Jakhal - Hisar (79 km)
|
RE
|
80.0
|
|
90.
|
Railway Electrification
|
Chhapra-Ballia-Ghazipur-Varanasi-Allahabad RE (330 km)
|
RE
|
330
|
|
91.
|
Railway Electrification
|
Guntakal-Kalluru RE (40 km)
|
RE
|
40
|
|
92.
|
Railway Electrification
|
Utretia - Rae Bareli - Amethi - Janghai RE (214 km)
|
RE
|
214
|
|
93.
|
Railway Electrification
|
Daund-Baramati (44 km)
|
RE
|
44
|
|
94.
|
Railway Electrification
|
Amla-Chhindwara-Kalumna
|
RE
|
257
|
|
95.
|
Railway Electrification
|
Raipur-Titlagarh (203 km) {Part of Vizianagaram - Rayagada - Titlagarh - Raipur (465 km)}
|
RE
|
203
|
|
96.
|
Railway Electrification
|
Rajpura - Dhuri - Lehra Mohabat (151 km)
|
RE
|
151
|
|
97.
|
Railway Electrification
|
Guntakal - Bellary - Hospet incl. Tornagallu - Ranjitpura Branch Line (138 km)
|
RE
|
138
|
|
98.
|
Railway Electrification
|
Wani- Pimpalkutti RE (66 km)
|
RE
|
66
|
|
99.
|
Railway Electrification
|
Manoharabad- Medchal (14 km)
|
RE
|
14
|
|
100.
|
Railway Electrification
|
Yalahanka-Penukonda (120.55 km)-Doubling
|
RE
|
-
|
|
101.
|
Railway Electrification
|
Jakhal - Dhuri - Ludhiana (123 km)
|
RE
|
123
|
|
102.
|
Railway Electrification
|
Guna-Gwalior (227 km)
|
RE
|
227
|
|
103.
|
Railway Electrification
|
Rani-Palanpur 166 km
|
RE
|
166
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
104.
|
Railway Electrification
|
Villupuram-Cuddalore Port-Mayiladuturai-Thanjavur & Mayiladuturai-Thiruvarur (228 km)
|
RE
|
228
|
|
105.
|
Railway Electrification
|
Raebareli-Unchahar incl. Dalmau-Daryapur (63 km)
|
RE
|
63
|
|
106.
|
Railway Electrification
|
Raninagar Jalpaigudi-New Bongaigaon - Guwahati (Incl) RE (382 km) (Part of Barauni - Katihar - Guwahati Incl. Katihar - Barsoi (836 km) RE
|
RE
|
374.98
|
|
107.
|
Railway Electrification
|
Chikjajur-Bellary RE (184 km)
|
RE
|
183.15
|
|
108.
|
Railway Electrification
|
Bengaluru-Omalur Via Hosur RE (196 km)
|
RE
|
196.00
|
|
109.
|
Railway Electrification
|
Utratia-Raebareli-Amethi 2nd line RE (126 km)
|
RE
|
126.00
|
|
110.
|
Railway Electrification
|
RE of Sambalpur-Titlagarh Doubling project (96.596 km)
|
RE
|
96.60
|
|
111.
|
Railway Electrification
|
Palanpur-Samakhiali (247.73 km) RE
|
RE
|
247.73
|
|
112.
|
Railway Electrification
|
Kasganj-Bareilly-Bhojipura-Daliganj RE (401 km)
|
RE
|
401
|
|
113.
|
Railway Electrification
|
RE of Dhasa - Jetalsar (104.44 km)
|
RE
|
104.44
|
|
114.
|
Railway Electrification
|
RE of Ahmedabad- Botad (170.48 km)
|
RE
|
170.48
|
|
115.
|
Deposit
|
RE of NTPC siding at Hotgi Station (37 km)
|
RE
|
34.41
|
|
116.
|
Deposit
|
Electrification of IOCL Siding at Pakni (4 km)
|
RE
|
4.15
|
|
117.
|
Deposit
|
Electrification of Ultra Tech Cement Siding at Hotgi (8km)
|
RE
|
9.75
|
|
118.
|
Deposit
|
Electrification of Chettinad Cement Siding at Tilati (7.1km)
|
RE
|
5.9
|
|
119.
|
Central Railway
|
Latur- Setting up of coach manufacturing factory
|
WKSP
|
-
|
|
120.
|
Eastern Railway
|
Civil Engineering Works in Connection with Diesel Loco Component Factory, Dankuni
|
WKSP
|
-
|
|
121.
|
Eastern Railway
|
Dankuni - Setting Up of Electric Loco Assembly and Ancillary Unit of CLW
|
WKSP
|
-
|
|
122.
|
Eastern Railway
|
Ranaghat (EMU Car Shed)-Inspection bay for 15 coach maintenance facilities
|
WKSP
|
-
|
|
123.
|
Eastern Railway
|
Jheel Siding Coaching Depot- Infrastructure development
|
WKSP
|
-
|
|
124.
|
East Central Railway
|
Barauni - 250 High Horse Power Loco Shed
|
WKSP
|
-
|
|
125.
|
East Central Railway
|
Gaya -Setting up New MEMU car shed for maintaining 30 rakes of 16 coaches
|
WKSP
|
-
|
|
126.
|
East Coast Railway
|
Vadlapudi- Wagon PoH Workshop of 200 Nos Capacity Near Duvvada Station
|
WKSP
|
-
|
|
127.
|
East Coast Railway
|
Khurda Road - Construction of main line electrical multiple unit car shed (Phase-2)
|
WKSP
|
-
|
|
128.
|
North Central Railway
|
Kanpur - Construction of MEMU Car shed
|
WKSP
|
-
|
|
129.
|
North Central Railway
|
Jhansi-Setting up of coach periodic overhauling and refurbishment workshop
|
WKSP
|
-
|
|
130.
|
North Eastern Railway
|
Saidpur Bhitri- Setting up of Electric Loco Shed to home 200 Locos
|
WKSP
|
-
|
|
131.
|
North Eastern Railway
|
Dullahapur Yard - Provision of tower wagon periodic overhauling shed
|
WKSP
|
-
|
|
132.
|
Northern Railway
|
Sonipat-Setting up of coach periodical overhauling and refurbishment workshop
|
WKSP
|
-
|
|
133.
|
South Eastern Railway
|
Setting Up of Diesel Multiple Unit (DMU) Manufacturing Factory at Sankrail / Haldia
|
WKSP
|
-
|
|
134.
|
DLW
|
Varanasi - Augmentation of Production Capacity from 200 To 250 High HP Locos Per Year
|
WKSP
|
-
|
|
135.
|
North Eastern Railway
|
Aunrihar - DEMU Shed
|
WKSP
|
-
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
136.
|
South Central Railway
|
Workshop for Manufacture of Flat Bogies for LHB Design Coaches, Yadgir
|
WKSP
|
-
|
|
137.
|
Western Railway
|
Vadodara - Setting up of New PoH Shop for Electrical Locos
|
WKSP
|
-
|
|
138.
|
South Central Railway
|
Hyderabad-Secunderabad - Multi modal transport system (Phase-II)-MTP
|
MTP
|
78
|
|
139.
|
METKOL
|
MM of Existing Corridor Noparanagar-Baranagar- Daksineshwar
|
MTP
|
4.14
|
|
140.
|
Eastern Railway
|
Barddhaman Yard - 4-lane road over bridge in lieu of 2-lane road over bridge No. 213
|
ROB
|
-
|
|
141.
|
Southern Railway
|
Srirangam-Tiruchchirapalli Town - 4-lane road over bridge in lieu of 2- lane bridge No.380-A
|
ROB
|
-
|
|
142.
|
North Western Railway
|
IOC Siding at Salawas (Deposit Work)
|
Others
|
2.82
|
|
143.
|
South Central Railway
|
Secunderabad- Upgradation of facilities at Centralised Training Academy for Railway Accounts
|
TRG
|
-
|
|
144.
|
South Central Railway
|
Moula Ali - Setting Up of Indian Railway Institute of Finance Management
|
TRG
|
-
|
|
145.
|
South Central Railway
|
Lallaguda (Carriage Workshop)- Replacement of 100-Year-Old Administrative Building
|
OSW
|
-
|
|
146.
|
South Western Railway
|
New Station Building at Belguam
|
OSW
|
-
|
|
147.
|
South Western Railway
|
Second Entry Station Building at Belguam
|
OSW
|
-
|
|
148.
|
South Western Railway
|
Proposed Coaching Depot at Belgaum
|
OSW
|
-
|
|
149.
|
South Western Railway
|
Yard Remodelling Works at Belgaum
|
OSW
|
-
|
|
150.
|
North Western Railway
|
Madar - Palanpur - Removing of PSR (Kms 589/1 to 590/1)
|
Track Renewal
|
-
|
|
151.
|
North Central Railway
|
Jhansi-Garhmau, Orai-Ata, Ata-Kalpi & Pokhrayan- Lalpur - Splitting of longer block sections
|
TF
|
-
|
|
152.
|
North Central Railway
|
Paman-Bhimsen - New B-class station
|
TF
|
-
|
|
153.
|
South Central Railway
|
Umdanagar-Timmapur - New crossing station
|
TFC
|
-
|
|
154.
|
Western Railway
|
Sabarmati-Botad-subways in lieu of level crossing-23 Nos.
|
RSW
|
-
|
|
155.
|
Western Railway
|
Sabarmati-Botad-Subways in lieu of LCs-14 Nos.
|
RSW
|
-
|
|
156.
|
Western Railway
|
Dhasa-Jetalsar-Subways in lieu of Level Crossing-35 Nos.
|
RSW
|
-
|
|
157.
|
Northern Railway
|
Final Location Survey for New Line Connectivity to Char Dham (327 km)
|
FLS
|
-
|
|
158.
|
North Eastern Railway
|
Daraganj- Rebuiding (Bridge No. 111 on Ganga)
|
BRWG
|
1.934
|
|
159.
|
Southern Railway
|
Pamban Bridge (Lifting Span Bridge)
|
BRWG
|
3.959
|
|
Following projects Completed in 2025-26:
|
|
160.
|
South East Central Railway
|
Dallirajhara - Rowghat New Line Project
|
New Line
|
95
|
3.3 Total project length completed:
Cumulatively, RVNL has completed a total of 6567.94 km of doubling, 2120.36 km of gauge conversion, 655.18 km of new lines, 7743.30 km of pure Railway Electrification, 4590.53 km RE as part of NL/GC/DL and 84.40 km of Metropolitan Transport Project (MTP). Thus, as on 31.3.2026, 17171.19 km of project length of 185 sanctioned projects assigned to RVNL, have been completed.
3.4 Project length completed during 2025-26:
During 2025-26, 110.57 km (31.69 km of New Line, 78.88 of Doubling), Railway Electrification of 110.57 km was also carried out in other than specific Railway Electrification projects as part of Doubling.
3.4.1 Sections completed under New Line Plan Head: During the year, 31.69 km of New Line was completed, the details are given below:
3.4.1.1 Bhanupalli - Bilaspur - Beri (63.1 km) : During the year, Bhanupalli - Thaluah Yard (7.15 km) section was completed in November 2025.
3.4.1.2 Angul - Sukinda (106.69 km): During the year, Talcher Road - Kamalanga (Route-E) (7.04 km) section was completed in January 2026.
3.4.1.3 Dallirajhara - Rowghat (95 km): During the year, Taroki - Rowghat (17.5 km) section was completed in March 2026.
3.4.2 Sections completed under Doubling Plan Head: During the year, 78.88 km of Doubling was completed, the details are given below:
3.4.2.1 Vizianagaram - Sambalpur (Titlagarh) 3rd Line (263.64 km): During the year, 54.27 km of project length was completed. Komatpalli (KMX) - Donkinavalasa (DNV) (9.82 km) was completed in May 2025, Gajapatinagaram (GPI) - Komatpalli (KMX) (9.57 km) was completed in June 2025, Theruvali Jn. (THV) - Bissamcuttack (BMCK) (18.5) was completed in September 2025, Garudaballi (GRBL) - Gajapatinagaram (GPI) (10.51 km) was completed in October 2025 and Gotlam (GTLM) - Garudaballi (GRBL) (5.87 km) was completed in December 2025.
3.4.2.2 Bhatni- Aunrihar (118 km): During the year, 20.35 km of project length was completed. Mau - Pipridih (10.86 km) was completed in June 2025 and Salempur - Lar Road (9.49 km) was completed in August 2025.
3.4.2.3 Hospet - Hubli - Tinaighat (335.08 km): During the year, Cansaulim - Sankaval (4.26 km) was completed in March 2026.
Projects Fully Commissioned and Handed over to Railways:
Out of 160 projects completed so far, 158 projects have been
fully commissioned and handed over to Railways for operations
and maintenance.
The list of 158 projects commissioned till March 2026 is as under:
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
1.
|
Central Railway
|
Diva - Kalyan 5th & 6th Line
|
Doubling
|
11
|
|
2.
|
Central Railway
|
Pakni - Mohol Doubling
|
Doubling
|
17
|
|
3.
|
Central Railway
|
Panvel - Jasai JNPT Doubling
|
Doubling
|
28.5
|
|
4.
|
Central Railway
|
Pakni - Solapur Doubling
|
Doubling
|
16.28
|
|
5.
|
Central Railway & SCR
|
Daund- Gulbarga- Doubling (224.9 km) and Pune- Guntakal -Electrification (641.37 km)
|
Doubling
|
224.9
|
|
6.
|
Eastern Railway
|
Gurup - Saktigarh Extn of 3rd Line
|
Doubling
|
26
|
|
7.
|
East Central Railway
|
Barauni - Tilrath Bypass Doubling
|
Doubling
|
8.3
|
|
8.
|
East Coast Railway
|
Talcher-Cuttack-Paradeep Doubling with 2nd Bridge on Rivers Birupa & Mahanadi
|
Doubling
|
3
|
|
9.
|
East Coast Railway
|
Cuttack - Barang Doubling
|
Doubling
|
14.3
|
|
10.
|
East Coast Railway
|
Jakhapura- Haridaspur 3rd Line
|
Doubling
|
23.3
|
|
11.
|
East Coast Railway
|
Rajatgarh-Barang - 3rd line
|
Doubling
|
31.3
|
|
12.
|
East Coast Railway
|
Sambalpur-Titlagarh (182 km)
|
Doubling
|
182.00
|
|
13.
|
East Coast Railway
|
Banspani-Daitari-Tomka-Jakhapura (180 km)
|
Doubling
|
180
|
|
14.
|
East Coast Railway
|
Khurda - Barang 3rd Line
|
Doubling
|
32.32
|
|
15.
|
East Coast Railway
|
Raipur-Titlagarh (203 km)
|
Doubling
|
203
|
|
16.
|
North Central Railway
|
Palwal - Bhuteswar 3rd Line
|
Doubling
|
81
|
|
17.
|
North Central Railway
|
Aligarh - Ghaziabad 3,d Line
|
Doubling
|
106.1
|
|
18.
|
North Central Railway
|
Bhimsen- Jhansi (206 km) with RE
|
Doubling
|
206
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
19.
|
North Eastern Railway
|
Janghai- Phahamau DL
|
Doubling
|
49.16
|
|
20.
|
North Eastern Railway
|
Varanasi- Madhosingh- Allahabad
|
Doubling
|
120.35
|
|
21.
|
North Western Railway
|
Bhagat Ki Kothi - Luni Doubling
|
Doubling
|
30.3
|
|
22.
|
North Western Railway
|
Rani-Keshav Ganj Doubling
|
Doubling
|
59.5
|
|
23.
|
North Western Railway
|
Karjoda - Palanpur Doubling
|
Doubling
|
5.4
|
|
24.
|
North Western Railway
|
Rewari- Manheru Doubling
|
Doubling
|
69.02
|
|
25.
|
North Western Railway
|
Abu Road - Sarotra Road Patch Doubling
|
Doubling
|
23.55
|
|
26.
|
North Western Railway
|
Abu Road - Swaroopganj Patch Doubling
|
Doubling
|
25.36
|
|
27.
|
North Western Railway
|
Sarotra Road-Karjoda - Patch doubling (23.59 km)
|
Doubling
|
23.59
|
|
28.
|
Northern Railway
|
New Delhi - Tilak Bridge 5th & 6th Line Doubling
|
Doubling
|
2.65
|
|
29.
|
Northern Railway
|
Utretia-Rae Bareli (65.6 km)
|
Doubling
|
68.04
|
|
30.
|
Northern Railway
|
Raebareli - Amethi (60.1 km)
|
Doubling
|
59.00
|
|
31.
|
Northern Railway
|
Rajpura- Bhatinda (172.64 km)
|
Doubling
|
173.38
|
|
32.
|
Southern Railway
|
Attipattu - Korukkupet 3rd Line
|
Doubling
|
18
|
|
33.
|
Southern Railway
|
Pattabiram - Tiruvallur 4th Line & Tiruvallur - Arakkonam 3rd Line
|
Doubling
|
41.89
|
|
34.
|
Southern Railway
|
Tiruvallur - Arakkonam 4th Line
|
Doubling
|
28
|
|
35.
|
Southern Railway
|
Villipuram-Dindigul Doubling
|
Doubling
|
273
|
|
36.
|
Southern Railway
|
Thanjavur-Ponmalai - Doubling
|
Doubling
|
46.96
|
|
37.
|
Southern Railway
|
Madurai-Maniyachi-Tuticorin (160 km)
|
Doubling
|
160
|
|
38.
|
Southern Railway
|
Maniyachi-Nagercoil DL
|
Doubling
|
102
|
|
39.
|
South Central Railway
|
Pullampet - Balapalle Ph I of Gooty - Renigunta Doubling
|
Doubling
|
41
|
|
40.
|
South Central Railway
|
Krishnapatnam - Venkatachalam Doubling With RE
|
Doubling
|
16.5
|
|
41.
|
South Central Railway
|
Gooty - Renigunta Patch Doubling
|
Doubling
|
151
|
|
42.
|
South Central Railway
|
Raichur - Guntakal Doubling
|
Doubling
|
81.0
|
|
43.
|
South Central Railway
|
Guntur-Tenali - Doubling with electrification (24.38 km)
|
Doubling
|
25
|
|
44.
|
South Central Railway
|
Secunderabad-Mehboobnagar (85.24 km)
|
Doubling
|
85.70
|
|
45.
|
South Central Railway
|
Vijaywada-Gudivada- Bhimavaram-Narasapur, Gudivada- Machlipatnam and Bhimavaram-Nidadavolu (221 km)
- Doubling with electrification
|
Doubling
|
221.00
|
|
46.
|
South Eastern Railway
|
Panskura - Kharagpur 3rd Line
|
Doubling
|
45
|
|
47.
|
South Eastern Railway
|
Panskura - Haldia Ph 1 Doubling
|
Doubling
|
14
|
|
48.
|
South Eastern Railway
|
Rajgoda - Tamluk (Jn. Cabin) Doubling
|
Doubling
|
13.5
|
|
49.
|
South Eastern Railway
|
Tikiapara - Santragachi Doubling
|
Doubling
|
5.6
|
|
50.
|
South Eastern Railway
|
Tamluk Jn. Cabin - Basulya Sutahata Doubling
|
Doubling
|
24.23
|
|
51.
|
South Eastern Railway
|
Goelkera-Monoharpur 3rd line (40 km)
|
Doubling
|
27.5
|
|
52.
|
South East Central Railway
|
Bilaspur - Urkura 3rd Line Doubling
|
Doubling
|
105
|
|
53.
|
South East Central Railway
|
Salka Road- Khongsara Patch Doubling
|
Doubling
|
26
|
|
54.
|
South East Central Railway
|
Khodri-Anuppur, with flyover at Bilaspur (61.6 km)
|
Doubling
|
61.6
|
|
55.
|
South Western Railway
|
Hospet - Guntakal Doubling
|
Doubling
|
115
|
|
56.
|
West Central Railway
|
Budni - Itarsi 3'd Line
|
Doubling
|
25.09
|
|
57.
|
West Central Railway
|
Barkhera- Habibganj - 3rd line (41.420 km)
|
Doubling
|
41.2
|
|
58.
|
West Central Railway
|
Bhopal-Bina - 3rd line (143 km)
|
Doubling
|
143
|
|
59.
|
West Central Railway
|
Bina -Kota (282.66 km) with RE
|
Doubling
|
282.66
|
|
60.
|
Western Railway
|
Palanpur- Samakhiali (247.73 km)
|
Doubling
|
247.3
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
61.
|
West Central Railway
|
Barkhera - Budni 3rd line
|
Doubling
|
26.5
|
|
62.
|
North Western Railway
|
Delhi - Rewari Gauge Conversion
|
GC
|
94.2
|
|
63.
|
North Eastern Railway
|
Lucknow-Pilibhit via Sitapur, Lakhimpur (262.76 km)
|
GC
|
262.76
|
|
64.
|
North Western Railway
|
Ajmer - Phulera - Ringus - Rewari Gauge Conversion
|
GC
|
295
|
|
65.
|
North Western Railway
|
Bhildi - Samdari Gauge Conversion
|
GC
|
223
|
|
66.
|
Southern Railway
|
Thanjavur - Villupuram Gauge Conversion
|
GC
|
192
|
|
67.
|
Southern Railway
|
Cuddalore - Salem Gauge Conversion
|
GC
|
193
|
|
68.
|
South Western Railway
|
Arasikere-Hassan-Mangalore Gauge Conversion
|
GC
|
230
|
|
69.
|
Western Railway
|
Bharuch - Samni - Dahej Gauge Conversion
|
GC
|
62
|
|
70.
|
Western Railway
|
Gandhidham - Palanpur Gauge Conversion
|
GC
|
301
|
|
71.
|
Western Railway
|
Ahmedabad- Botad (170.48 km)
|
GC
|
166.09
|
|
72.
|
Western Railway
|
Dhasa- Jetalsar (104.44 km)
|
GC
|
106.69
|
|
73.
|
East Coast Railway
|
Daitari - Banspani New Line
|
NL
|
155
|
|
74.
|
East Coast Railway
|
Haridaspur-Paradeep (82 km)
|
NL
|
82
|
|
75.
|
East Coast Railway
|
Angul-Sukinda Road (98.7 km)
|
NL
|
98.7
|
|
76.
|
North Eastern Railway
|
Mau-Gazipur-Tarighat New Line
|
NL
|
16.79
|
|
77.
|
Southern Railway
|
Vallarpadam - Idapally New Line
|
NL
|
9
|
|
78.
|
South Central Railway
|
Obulavaripalle - Krishnapatnam New Line
|
NL
|
121
|
|
79.
|
Railway Electrification
|
Tomka -Banspani - RE
|
RE
|
144
|
|
80.
|
Railway Electrification
|
Kharagpur (Nimpura) - Bhubaneswar Including Branch Line of Talcher - Cuttack - Paradeep
|
RE
|
581
|
|
81.
|
Railway Electrification
|
Bhubaneswar - Kottavalasa
|
RE
|
417
|
|
82.
|
Railway Electrification
|
Reningunta - Guntakal RE
|
RE
|
308
|
|
83.
|
Railway Electrification
|
Bharuch - Samni - Dahej RE
|
RE
|
64
|
|
84.
|
Railway Electrification
|
Daund-Manmad Incl. Puntamba- Shirdi - RE
|
RE
|
255
|
|
85.
|
Railway Electrification
|
Yelahanka - Dharmavaram - Gooty RE
|
RE
|
306
|
|
86.
|
Railway Electrification
|
Manheru- Hisar (74 km)
|
RE
|
74.0
|
|
87.
|
Railway Electrification
|
Jakhal - Hisar (79 km)
|
RE
|
80.0
|
|
88.
|
Railway Electrification
|
Chhapra-Ballia-Ghazipur-Varanasi-Allahabad (330 km)
|
RE
|
330
|
|
89.
|
Railway Electrification
|
Guntakal-Kalluru (40 km)
|
RE
|
40
|
|
90.
|
Railway Electrification
|
Daund- Bramati (44 km)
|
RE
|
44
|
|
91.
|
Railway Electrification
|
Titlagarh (Excl)-Raipur -RE
|
RE
|
203
|
|
92.
|
Railway Electrification
|
Utretia- Rae Bareli- Amethi- Janghai RE
|
RE
|
214
|
|
93.
|
Railway Electrification
|
Hospet - Guntakal And Tomagallu - Ranjitpura
|
RE
|
138
|
|
94.
|
Railway Electrification
|
Wani-Pimpalkutti (66 km)
|
RE
|
66
|
|
95.
|
Railway Electrification
|
Yalahanka-Penukonda (120.55 km)-Doubling
|
RE
|
-
|
|
96.
|
Railway Electrification
|
Rajpura - Dhuri - Lehra Mohabat (151 km)
|
RE
|
151
|
|
97.
|
Railway Electrification
|
Jakhal - Dhuri - Ludhiana (123 km)
|
RE
|
123
|
|
98.
|
Railway Electrification
|
Guna-Gwalior (227 km)
|
RE
|
227
|
|
99.
|
Railway Electrification
|
Rani-Palanpur 166 km
|
RE
|
166
|
|
100.
|
Railway Electrification
|
Manoharabad- Medchal (14 km)
|
RE
|
14
|
|
101.
|
Railway Electrification
|
Amla - Chhindwara - Kalumna (257 km)
|
RE
|
257
|
|
102.
|
Railway Electrification
|
Villupuram-Cuddalore Port-Mayiladuturai-Thanjavur & Mayiladuturai-Thiruvarur (228 km)
|
RE
|
228
|
|
103.
|
Railway Electrification
|
Raebareli-Unchahar incl. Dalmau-Daryapur (63 km)
|
RE
|
63
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
104.
|
Railway Electrification
|
Raninagar Jalpaigudi-New Bongaigaon (incl.)-Guwahati (incl.)-382 rkm {Part of Barauni-Katihar-Guwahati incl Katihar-Barsoi (836 km)}
|
RE
|
374.98
|
|
105.
|
Railway Electrification
|
Chikjajur-Bellary (184 rkm)
|
RE
|
183.15
|
|
106.
|
Railway Electrification
|
Bengaluru-Omalur via Hosur (196 rkm)
|
RE
|
196.00
|
|
107.
|
Railway Electrification
|
2nd Line Utratia-Raebareli-Amethi (126 rkm) (Northern Railway) (PB#135/2018-19/CORE)
|
RE
|
126.00
|
|
108.
|
Railway Electrification
|
RE of Sambalpur-Titlagarh Doubling project (96.596 km)
|
RE
|
96.60
|
|
109.
|
Railway Electrification
|
Kasganj-Bareilly-Bhojipura-Daliganj RE (401 km)
|
RE
|
401
|
|
110.
|
Western Railway
|
Palanpur- Samakhiali (247.73 km) RE
|
RE
|
247.73
|
|
111.
|
Western Railway
|
RE of Dhasa - Jetalsar (104.44 km)
|
RE
|
104.44
|
|
112.
|
Western Railway
|
RE of Ahmedabad- Botad (170.48 km)
|
RE
|
170.48
|
|
113.
|
Deposit
|
RE of NTPC siding at Hotgi Station (37 km)
|
RE
|
34.41
|
|
114.
|
Central Railway
|
Latur- Setting up of coach manufacturing factory
|
WKSP
|
-
|
|
115.
|
Eastern Railway
|
Civil Engineering Works in Connection with Diesel Loco Component Factory, Dankuni
|
WKSP
|
-
|
|
116.
|
Eastern Railway
|
Dankuni - Setting Up of Electric Loco Assembly and Ancillary Unit of CLW
|
WKSP
|
-
|
|
117.
|
Eastern Railway
|
Ranaghat (EMU Car Shed)-Inspection bay for 15 coach maintenance facilities
|
WKSP
|
-
|
|
118.
|
Eastern Railway
|
Jheel Siding Coaching Depot- Infrastructure development
|
WKSP
|
-
|
|
119.
|
East Central Railway
|
Barauni - 250 High Horse Power Loco Shed
|
WKSP
|
-
|
|
120.
|
East Central Railway
|
Gaya -Setting up New MEMU car shed for maintaining 30 rakes of 16 coaches
|
WKSP
|
-
|
|
121.
|
East Coast Railway
|
Vadlapudi - Wagon PoH Workshop of 200 Nos Capacity Near Duvvada Station
|
WKSP
|
-
|
|
122.
|
East Coast Railway
|
Khurda Road - Construction of main line electrical multiple unit car shed (Phase-2)
|
WKSP
|
-
|
|
123.
|
North Central Railway
|
Kanpur - Construction of MEMU Car shed
|
WKSP
|
-
|
|
124.
|
North Central Railway
|
Jhansi-Setting up of coach periodic overhauling and refurbishment workshop
|
WKSP
|
-
|
|
125.
\
|
Northern Railway
|
Sonipat-Setting up of coach periodical overhauling and refurbishment workshop
|
WKSP
|
-
|
|
126.
|
South Central Railway
|
Workshop for Manufacture of Flat Bogies for LHB Design Coaches, Yadgir
|
WKSP
|
-
|
|
127.
|
South Eastern Railway
|
Setting Up of Diesel Multiple Unit (DMU) Manufacturing Factory at Sankrail / Haldia
|
WKSP
|
-
|
|
128.
|
DLW
|
Varanasi - Augmentation of Production Capacity from 200 to 250 High HP Locos Per Year
|
WKSP
|
-
|
|
129.
|
North Eastern Railway
|
Aunrihar - DEMU Shed
|
WKSP
|
-
|
|
130.
|
North Eastern Railway
|
Saidpur Bhitri- Setting up of electric loco shed to home 200 locos
|
WKSP
|
-
|
|
131.
|
North Eastern Railway
|
Dullahapur Yard - Provision of tower wagon periodic overhauling shed
|
WKSP
|
-
|
|
132.
|
Western Railway
|
Vadodara - Setting up of New PoH Shop for Electrical Locos
|
WKSP
|
-
|
|
133.
|
South Central Railway
|
Hyderabad-Secunderabad - Multi modal transport system (Phase-II)-MTP
|
MTP
|
78
|
|
134.
|
METKOL
|
MM of Existing Corridor Noparanagar-Baranagar- Daksineshwar
|
MTP
|
4.14
|
|
S.
No.
|
Railway
|
Project Name
|
Type of Project
|
Length (km)
|
|
135.
|
Eastern Railway
|
Barddhaman Yard - 4-lane road over bridge in lieu of 2-lane road over bridge No. 213
|
ROB
|
-
|
|
136.
|
Southern Railway
|
Srirangam-Tiruchchirapalli Town - 4-lane road over bridge in lieu of 2- lane bridge No.380-A
|
ROB
|
-
|
|
137.
|
Deposit
|
Electrification of IOC Siding at Salawas (Deposit Work)
|
RE
|
2.82
|
|
138.
|
Deposit
|
Electrification of IOCL Siding at Pakni (4 km)
|
RE
|
4.15
|
|
139.
|
Deposit
|
Electrification of Ultra Tech Cement Siding at Hotgi (8km)
|
RE
|
9.75
|
|
140.
|
Deposit
|
Electrification of Chettinad Cement Siding at Tilati (7.1km)
|
RE
|
5.9
|
|
141.
|
South Central Railway
|
Secunderabad- Upgradation of facilities at Centralised Training Academy for Railway Accounts
|
OSW
|
-
|
|
142.
|
North Western Railway
|
Madar - Palanpur - Removing of PSR (Kms 589/1 to 590/1)
|
TR
|
-
|
|
143.
|
South Central Railway
|
Moula Ali - Setting Up of Indian Railway Institute of Finance Management
|
TRG
|
-
|
|
144.
|
South Central Railway
|
Lallaguda (Carriage Workshop)- Replacement of 100-Year-Old Administrative Building
|
OSW
|
-
|
|
145.
|
South Western Railway
|
New Station Building at Belguam
|
OSW
|
-
|
|
146.
|
South Western Railway
|
Second Entry Station Building at Belguam
|
OSW
|
-
|
|
147.
|
South Western Railway
|
Proposed Coaching Depot at Belgaum
|
OSW
|
-
|
|
148.
|
South Western Railway
|
Yard Remodelling Works at Belgaum
|
OSW
|
-
|
|
149.
|
North Central Railway
|
Jhansi-Garhmau, Orai-Ata, Ata-Kalpi & Pokhrayan-Lalpur - Splitting of longer block sections
|
TF
|
-
|
|
150.
|
North Central Railway
|
Paman-Bhimsen - New B-class station
|
TF
|
-
|
|
151.
|
South Central Railway
|
Umdanagar- Timmapur - New Crossing Station
|
TFC
|
-
|
|
152.
|
Western Railway
|
Sabarmati-Botad-subways in lieu of level crossing-23 Nos.
|
RSW
|
-
|
|
153.
|
Western Railway
|
Sabarmati-Botad-Subways in lieu of LCs-14 Nos.
|
RSW
|
-
|
|
154.
|
Western Railway
|
Dhasa-Jetalsar-Subways in lieu of Level Crossing-35 Nos.
|
RSW
|
-
|
|
155.
|
Northern Railway
|
Final Location Survey for New Line Connectivity to Char Dham (327 km)
|
FLS
|
-
|
|
156.
|
North Eastern Railway
|
Daraganj- Rebuiding (Bridge No. 111 on Ganga)
|
BRWG
|
1.934
|
|
157.
|
Southern Railway
|
Pamban Bridge (Lifting Span Bridge)
|
BRWG
|
3.959
|
|
Project commissioned in 2025-26 is as under:
|
|
158.
|
North Eastern Railway
|
Phephna-Indara, Mau-Shahganj (excluding Indara-Mau) (150.28 km)
|
Doubling
|
150.28
|
3.5 Sections of Projects Commissioned and handed over to Railways in 2025-26:
3.5.1 In 2025-26, 173.82 km sections were commissioned consisting of 12.14 km of New Line and 161.68 km of Doubling handed over to Zonal Railways for operations. Railway Electrification of 173.82 km was also carried out in other than specific Railway Electrification projects as part of Doubling, the details are given below:
|
SN
|
Plan
Head
|
Name of work
|
Section Targeted
|
Section
Length
(km)
|
Total Length
(km)
|
Zonal
Railway
|
|
1
|
NL
|
Angul - Sukinda
|
Talcher Road-Kamalanga (Route-E)
|
7.042
|
7.042
|
ECoR
|
|
2
|
NL
|
Neora- Daniawan & Barbigha & sheikpura
|
Barbigha- Sarsajamalpur
|
5.1
|
5.1
|
ECR
|
| |
|
|
Total New Line:
|
12.14
|
12.14
|
|
|
3
|
DL
|
Vizianagaram- Titlagarh 3rd line
|
Parvatipuram-Sitanagaram-Bobbili-
Donkinavalasa
|
36.05
|
43.23
|
ECoR
|
| |
|
Project
|
Ladda-Jimidipeta
|
7.18
|
|
|
|
SN
|
Plan
Head
|
Name of work
|
Section Targeted
|
Section
Length
(km)
|
Total Length
(km)
|
Zonal
Railway
|
|
4
|
DL
|
Vijayawada-Gudur 3rd
|
Singarayakonda - Surareddipalem
|
17.8
|
50.05
|
SCR
|
| |
|
Line with RE Project
|
Tsunduru-Tenali-Duggirala-
Pedavadlapudi
|
32.25
|
|
|
|
5
|
DL
|
Bhatani - Aunrihar
|
Mau-Pipridih-Dullahpur
|
18.28
|
32.81
|
NER
|
| |
|
Doubling
|
Peokol-Salempur-Lar Road
|
14.53
|
|
|
|
6
|
DL
|
Phephna-Indara, Mau- Shahganj (excluding Indara-Mau)
|
Mau-Khurahat
|
12.53
|
12.53
|
NER
|
|
7
|
DL
|
Sonnagar - Patratu 3
|
Bendi-Kumandi
|
6.74
|
18.51
|
ECR
|
| |
|
rd Line
|
Muhammad Ganj-Satbahini-Untari Road
|
11.77
|
|
|
|
8
|
DL
|
Kharagpur-Adityapur 3rd line project
|
Salgajahri East- Salgajhari West (West End of LC 139)
|
3.05
|
3.05
|
SER
|
|
9
|
DL
|
RPJ-BTI Doubling
|
DUI yard remodelling
|
1.5
|
1.5
|
NR
|
| |
|
|
Total Doubling:
|
161.68
|
161.68
|
|
| |
|
|
G. Total
|
173.82
|
173.82
|
|
3.6 Signalling and Telecommunication:
The Signaling & Telecommunication (S&T) domain provides appropriate and cost-effective solutions for efficient and safe operation of trains on Indian Railways. RVNL promotes use of modern technologies on Indian Railways namely Electronic Interlocking (EI), Digital Axle Counters, Fiber Optic Cable Network, Automatic Block Signaling, ETCS L1/L2/L3, IOT based Diagnostic & Predictive Maintenance systems etc.
The technological advancement is aimed to achieve high level of safety in train operations, availability of system and increased speeds of trains with minimum head ways. This ensures the efficient punctual operation of Freight as well as of Coaching Trains. This has resulted in reduction of turnaround in freight transportation. With continuous and tireless effort of S&T vertical of RVNL in Railway Infrastructure, Indian Railways is able to achieve increase in freight loading and operation of large number of passenger trains across the length and breadth of the country.
RVNL is a major contributor in providing EI installations on Indian Railways in connection with Doubling, 3rd Line, New Line and Gauge Conversion. Keeping its tradition high, during FY 2025-26, RVNL has commissioned New Electronic Interlocking and alteration in existing Electronic Interlocking at 48 Stations on Indian Railways.
RVNL has also commissioned 7 nos. Major Yard remodeling work on Indian Railways viz. Jakhapura, Milavittan, Manoharpur, Tenali, Sambalpur, Mathura and Dhuri stations with routes varying from 200 to 600+ Routes.
RVNL has taken up 55 Nos. of Non-Interlocking (NIs) of stations for commissioning of Doubling, 3rd Line and New Line projects during the year. RVNL has also commissioned
the 19 numbers of IBS, 379 Automatic Signalling using Electronic Interlocking and 29 Nos of mid-section level crossing gates have been interlocked with signals to improve safety of road user. Not only on the Signalling front, RVNL has also completed the incredible achievement in the area of telecommunication by providing 2195.7 km of Fiber Optic Network and 6 Quad Cable network in IR and and 5700 Km of Fiber Optic Network Cable network in BSNL (as part of Bharatnet Project UP East & UP West) during the year.
RVNL equiped with a strong team of IRSTELO license holders who are experienced to approve Logic & Interface Circuits and design drawings of all types of Railway signaling systems in-house. So far, RVNL has checked Interface Circuits of 16 stations and Logic Circuits of 6 stations of ECR and NCR. Moreover, RVNL Design team has checked Axle Counter Circuit of 1 no. station viz. BENDI in ECR. This has reduced significantly the workload of Zonal Railways Design team and expedited the approval process of Logic & Interface Circuits. This has resulted in timely commissioning of large number of stations by RVNL to adhere the target set by Railway Board.
RVNL has participated in various tenders of Automatic Signalling, Replacement of Panel Interlocking with EI, Vedio Survelliance System and KAVACH of Zonal Railways and has been awarded works of C531 crore of South East Central Railway , South Western Railway and Southern Railway during FY 2025-26.
Having played a very vital role in providing large nos. of signaling installations in connection with large infrastructure projects on Indian Railway, Signaling & Telecommunication vertical is on the lookout for opportunities in various signalling and telecom sector of Railways & other industries within India & abroad.
3.7 Projects under implementation:
There are 141 projects under various stages of implementation by RVNL.
3.7.1 The details of 27 projects assigned by Ministry of Railways to RVNL till March 2026 and which are under implementation are as under:
|
S.
No.
|
Railway
|
Name of Project
|
Plan Head
|
|
1.
|
ECR
|
Dhanbad-Sonnagar (Patratu-Sonnagar) - 3rd line (291 km)
|
Doubling
|
|
2.
|
ECoR
|
Vizianagaram-Sambhalpur (Titlagarh) 3rd line
|
Doubling
|
|
3.
|
NCR
|
Mathura-Jhansi 3rd line
|
Doubling
|
|
4.
|
NER
|
Bhatni - Aunrihar with electrification (125 km) (excl Indara - Mau (116.95 km))
|
Doubling
|
|
5.
|
SCR
|
Vijayawada-Gudur 3rd line
|
Doubling
|
|
6.
|
SER
|
Kharagpur (Nimpura)-Adityapur 3,d line (132 km)
|
Doubling
|
|
7.
|
SWR
|
Hospet-Hubli-Londa-Tinaighat-Vasco da Gama (352.28 km)
|
Doubling
|
|
8.
|
WR
|
Junagarh - Visavadar (42.28) km
|
Gauge
Conversion
|
|
9.
|
CR
|
Yevatmal- Nanded (206 km) NL
|
New Line
|
|
10.
|
ECR
|
Fatuah-Islampur incl. material modification for extension of new line from Neora to Daniawan; Daniawan to Biharsharif; Biharsharif to Barbigha; Barbigha to Sheikhpura
|
New Line
|
|
11.
|
NR
|
Rishikesh-Karnaprayag (125.09 km)
|
New Line
|
|
12.
|
NR
|
Bhanupalli-Bilaspur-Beri (63.1 km)
|
New Line
|
|
13.
|
SECR
|
Dallirajhara-Rowghat (90 km) {Part of Dallirajhara-Jagdalpur (235 km)}
|
New Line
|
|
14.
|
WCR
|
Indore-Jabalpur (342 km) NL sanctioned as Budhni-Indore (205 km)
|
New Line
|
|
15.
|
ER
|
Nabadwipghat-Nabadwipdham upto BB loop (9.58 km) {Part of Kalinarayanpur- Krishnanagar with Krishnanagar-Shantipur Nabadwipghat- GC, Krishnanagar- Chartala, MM for Krishnanagar Chapra-NL, Naihati-Ranaghat-3rd line, Nabadwipghat- Nabadwipdham upto BB loop (9.58 km), Ranaghat-Lalgola strengthening (bridge No.2)}
|
New Line
|
|
16.
|
CORE
|
Hospet - Hubli - Vasco da Gama (346 km)
|
RE
|
|
17.
|
SCR
|
Kazipet - Workshop for Wagon Periodical Overhauling
|
WKSP
|
|
18.
|
SR
|
Repair of S&T Workshop at Podanur, Tamil Nadu
|
WKSP
|
|
19.
|
ER
|
Samudragarh - Nabadwipdham - Road over bridge in lieu of level crossing No.14
|
RSW
|
|
20.
|
WR
|
National Rail & Transportation Institute at Vadodara (NAIR)
|
TRG
|
|
21.
|
WR
|
Construction of hostels in centralised training institutes (Umbrella Work 2019-20)
|
TRG
|
|
22.
|
WR
|
Infrastructure up-gradation of Training Institutes at NAIR Campus
|
TRG
|
|
23.
|
SECR
|
Direct Power Supply from Central Generating Agencies
|
OEW
|
|
24.
|
SCR
|
Ghatkesar-Raigir (Yadadri)-Extension of multi modal transportation system Phase-II
|
MTP
|
|
25.
|
METRO
|
Baranagar-Barrackpore & Dakshineswar - Construction of Metro Railway (14.5 km)
|
MTP
|
|
26.
|
METRO
|
Dum Dum Airport-New Garia via Rajerhat - Construction of Metro Railway (32 km) including Naupara (Ex.)-Baranagar (2.6 km) {Part of Dumdum-Baranagar Metro Railway sanctioned as MM to Dumdum-New Garia Metro Railway vide letter No. 96/Proj/C/5/1/ Pt. Dated 30.10.09}
|
MTP
|
|
27.
|
METRO
|
Joka-Binoy Badal Dinesh Bagh via Majerhat - Construction of Metro railway (16.72 km) incl material modification for extension from Joka Diamond Park (Phase-I)
|
MTP
|
3.7.2 The list of 104 projects awarded to RVNL through Competitive Bidding and under execution is as under:
3.7.2.1 The details of 91 projects awarded to RVNL through competitive biddings up to March 2025 are as under:
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
1.
|
MP Metro
|
Design and Construction of Elevated 10 km Viaduct and 09 Elevated Metro Stations including all Civil, Structural, Roof structure, MEP works, Architectural finishes, Fagade, etc for Indore Metro Rail Project.
|
Metro Works
|
|
2.
|
MP Metro
|
Design and Construction of 07 Elevated Metro Stations including Structures, Architectural Finishes, E&M Works etc. of Indore Metro Rail Project.
|
Metro Works
|
|
3.
|
NHIDCL
|
DPR Preparation for Highways in North-East Region in state of Nagaland for length of 200 KM.
|
DDC
|
|
4.
|
NHIDCL
|
DPR Preparation for Highways in North-East Region in state of Nagaland for length of 280 KM.
|
DDC
|
|
5.
|
NHIDCL
|
DPR Preparation for Highways in North-East Region in state of Mizoram for length of 740 KM.
|
DDC
|
|
6.
|
NFR
|
Construction of Single BG Tunnel Line No. 06 (approx. length 4930m) between Ch. 45800 to Ch. 50730 including Escape Tunnel (Total length 4600m), in connection with DMV-Kohima new BG Line Project
|
Civil
|
|
7.
|
GMRCL
|
Supply Installation Testing and Commissioning of Ballastless track (L -55 TKM) from Sarthana to Dream city in elevated and underground section for corriodr -1, Surat Metro, Phase -II
|
Civil
|
|
8.
|
NHAI
|
Construction Of 4 Laning of Nh-5 From Kaithlighat To Shakral Village (Shimla Bypass Package 1: From Km 128.835 To Km 146.300 For Design Length=17.465km) In Himachal Pradesh On Hybrid Annuity Mode.
|
Civil
|
|
9.
|
NHAI
|
Construction of 4 lane highway from Samarlakota to Achampeta Junction (from km. 0.000 to Km. 12.250) as a part of Kakinada port to NH-16 connectivity in the State of Andhra Pradesh under Bharatmala Pariyojana on EPC mode.
|
Civil
|
|
10.
|
AMC
|
Development of Kharicut Canal (Between Naroda Smashan Gruh & Vinzol Vehla) in AMC area Pakage-2: Kharicut Canal Development Navyug School Canal Crossing to Nidhipark Society (Ch. 2500 - Ch. 5000)
|
Civil
|
|
11.
|
AMC
|
Development of Kharicut Canal (Between Naroda Smashan Gruh & Vinzol Vehla) in AMC area Pakage-3: Kharicut Canal Development Nidhipark Society to Odhav Fire Station (Ch. 5000 - Ch. 7600)
|
Civil
|
|
12.
|
GoG-NH Division
|
Up gradation to Six Lane with Paved Shoulder of Sarkhej-Changodar Section of NH 8A (New NH 47) from KM 11+950 to KM 16+000 on EPC mode in the State of Gujarat
|
Civil
|
|
13.
|
CMRCL
|
Construction of Elevated Viaduct (approximate length of 10 km), nine (9) Elevated Metro Stations at Sholinganallur Lake-I, Sri Ponniamman Temple Sholinganallur Lake- II, Sathyabama University Semmeancheri-I, Semmeancheri-II, Gandhi Nagar, Navallur, Siruseri, Siruseri Sipcot-1 And Siruseri SIPCOT-2 and stabling viaduct at SIPCOT
|
Civil
|
|
14.
|
GMRCL
|
Construction of Bhesan Depot Cum Workshop Which Includes DCC, BCC and Associated E&M Works Under Corridor - C2, Bhesan To Saroli, For Surat Metro Rail Project Phase - 1, DC-2
|
Civil
|
|
15.
|
CORE
|
Design, Supply, Erection, Testing and Commissioning for OHE Modification Work in the existing 25 kV OHE for increasing speed potential to 160 KMPH under East Central Railway Pradhankhanta - Bandhua Section of Dhanbad Division (DHN).
|
Electrical
|
|
16.
|
MEA
|
Development of the UTF Harbour Project in Maldives
|
Civil
|
|
17.
|
Southern
Railway
|
Provision of Automatic Block Signalling with Dual MSDAC, EI/OC interface and Block Optimization in Arakkonam Junction(AJJ)-Nagari (NG) Section of Chennai (MAS) Division in Southern Railway (Reach-I).
|
S&T
|
|
18.
|
Southern
Railway
|
Provision of Automatic Block Signaling with Dual MSDAC, EI/OC Interface and Block Optimization in NAGARI(NG) - TADUKU(TDK) section and Replacement of EI/RRI at VEPAGUNTA (VGA) Station of CHENNAI (MAS) Division in Southern Railway (Reach-II).
|
S&T
|
|
19.
|
Southern
Railway
|
Provision of Automatic Block Signaling with Dual MSDAC, EI/OC Interface and Block Optimization in TADUKU(TDK)-RENIGUNTA (RU) section and Replacement of EI/RRI at TADUKU (TDK), PUDI (PUDI) & SRI VENKATA PERUMAL RAJU PURAM (SVF) Stations of CHENNAI (MAS) Division in Southern Railway (Reach-III).
|
S&T
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
20.
|
MPPKVVCL
|
Commissioning of 33 KV Line associated works such as 33 KV Line Bifurcation, 33 KV Line Interconnection and 33 KV Line Conductor Augmentation in Rewa, Satna, Sidhi, Singrauli, Sagar, Damoh, Chhatarpur, Panna and Tikamgarh Circles (Package-10) area of MPPKVVCL, Jabalpur under Revamped - Reforms - Based and Results - Linked Distribution Sector Scheme
|
Electrical
|
|
21.
|
GMRCL
|
Supply, Erection, Testing and Commissioning of power Supply Receiving & Distribution System, 750 V D Third Rail Traction Electrification and Scada system for Ahmedabad Metro
|
Electrical
|
|
22.
|
NWR
|
Provision of Automatic Block Signalling on Madar-Sakhun Section (51.13 Kms) of Jaipur Division over North Western Railway.
|
S&T
|
|
23.
|
IR
|
Manufacturing cum Maintenance of 200 nos. of Vande Bharat Trainsets including upgradation of the Government Manufacturing Units & Trainsets Depots
|
Manufacturing
|
|
24.
|
MPPKVVCL
|
Madhya Pradesh Madhya Kshetra Vidyut Vitaran Company Limited||MPMKVVCL - Civil
|
Electrical
|
|
25.
|
MPPKVVCL
|
Madhya Pradesh Poorva Kshetra: Revamped - Reforms - Based and Results - Linked Distribution Sector Scheme (RDSS) (Pkg-12)
|
Electrical
|
|
26.
|
NHAI
|
Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Highway from Sonepurbigha village to junction with NH-22 (Chatra Bypass) near Chatra from km 184.700 to km 222.000 under Bharatmala Pariyojana in the state of Jharkhand on Hybrid Annuity Mode (Package 8).
|
Civil
|
|
27.
|
NHAI
|
Construction of Six Lane Elevated Kona Expressway from Km. 0.145 to Km. 7.337 of NH- 117 in the state of West Bengal on EPC mode
|
Civil
|
|
28.
|
North
Central
Railway
|
Provision of EI based Automatic Signaling with continuous track circuiting and other associated works including suitable Indoor alteration in Electronic Interlocking/RRI/ PI stations enroute in Jhansi (incl)-Gwalior (Incl.) section of Jhansi Division of North Central Railway.
|
S&T
|
|
29.
|
GMRCL
|
Supply, Erection, Testing and Commissioning of Power Supply Receiving & Distribution System, 750 V Dc Third Rail Traction Electrification And Scada System For Surat Metro Rail Project Phase-I
|
Metro
|
|
30.
|
HORC
|
C-4: Composite Contract package in connection with New BG Railway Line of HORC project for: (i) Design & Construction of Twin Tunnel using NATM and Cut & Cover method from km 24.880 to km 29.580; (ii) Design & Installation of Ballastless Track (excluding supply of rails) from km 24.856 to km 29.680; (iii) Detailed Design, Supply, Installation, Testing & Commissioning of General Electrical Services including Supply, Erection, Testing and Commissioning of 11kV HT/LT Power and Control Cable Network, GIS Substation (11/0.433) kVA, Tunnel lighting system, etc. from km 24.880 to km 29.680; (iv) Design & Construction of Embankment, Bridges and other miscellaneous works from km 12.00 to km 18.00.
|
Civil
|
|
31.
|
MMRDA
|
Design, Manufacture, Supply, Installation, Testing and Commissioning of 2 nos. 110 kV receiving substation including 110 kV, 33kV & 25kV cabling work, complete 25kV overhead catenary system alongwith switching station, 33kV auxiliary power distribution system including 33/0.415 kV auxiliary sub-station (ASS) and complete SCADA system for main line & depot of Mumbai Metro line 2B of MMRDA. (IFB No: MMRDA/2B/MMRP/CA-40). Design, Manufacture, Supply, Installation, Testing and Commissioning of 2 nos. 110 kV
|
Electrical
|
|
32.
|
CMRL
|
Construction of Five (05) UG Stations at KMC(Kilpauk), Sterling Road, Nungambakkam, Gemini (Anna Flyover), Thousand Lights and Thousand Lights Cross Over Box and works other than Diaphragm wall of Two UG Stations at Royapettah Chetpet Metro in C3 of CMRL Phase-II Project. UG-03
|
Metro
|
|
33.
|
CMRL
|
Construction of Four Underground Stations at Dr. Radhakrishan Salai, Thirumayilai, Mandaiveli and Adyar Junction and Two Cross Passage Shafts and One Emergency Escape Shaft and works other than Diaphragm wall of One Underground Stations at Greenways Road Metro in Corridor-3 of CMRL Phase-II Project". UG -04
|
Metro
|
|
34.
|
CMRL
|
Construction of three (03) Underground Stations at Adyar Depot, Indira Nagar and Taramani Road Junction (Taramani) & Ramp and works other than Diaphragm wall of One Underground Station at Thiruvanmiyur Metro in Corridor-3 of CMRL Phase-II Project".- UG - 5
|
Metro
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
35.
|
MMRDA
|
Design, Manufacture, Supply, Installation, Testing and Commissioning of 2 nos. 110 kV receiving substation including 110 kV, 33kV & 25kV cabling work, complete 25kV overhead catenary system alongwith switching station, 33kV auxiliary power distribution system including 33/0.415 kV auxiliary sub-station (ASS) and complete SCADA system for main line & depot of Mumbai Metro line 2B of MMRDA. (IFB No: MMRDA/2B/MMRP/CA-40). Design, Manufacture, Supply, Installation, Testing and Commissioning of 2 nos. 110 kV
|
Electrical
|
|
36.
|
CMRL
|
Construction of Five (05) UG Stations at KMC(Kilpauk), Sterling Road, Nungambakkam, Gemini (Anna Flyover), Thousand Lights and Thousand Lights Cross Over Box and works other than Diaphragm wall of Two UG Stations at Royapettah Chetpet Metro in C3 of CMRL Phase-II Project. UG-03
|
Metro
|
|
37.
|
WATER
RESOURCES
ZONE,
UDAIPUR
|
Planning, Design and construction of main Canal and Structures including associated distribution system to provide Irrigation facility to 41903 ha. area through Piped Irrigation network for Upper High-Level Canal of Mahi Bajaj Sagar Project, Banswara (Raj) on Engineering, Procurement and Construction (E.P.C.) single Responsibility turnkey basis, including 10 years O&M.
|
Canal
|
|
38.
|
South
Central
Railway
|
Comprehensive Signalling and Telecommunication Works For Provision Of Automatic Block Signalling System In Balharshah - Makudi Section of Secunderabad Division In South Central Railway.
|
Signalling
|
|
39.
|
MPPKVVCL
|
Supply, Installation, Testing and Commissioning of New 11 KV Lines, LT Line on AB cable, Distribution Transformer Substation and Supporting works such as DPs, TPs, crossing etc. for separation of 11 KV mix Feeders & Mix DTRs under Revamped Reforms- based and Results-linked Distribution Sector (Package-16) in Chhatarpur circle of MPPKVVCL, Jabalpur Company Area.
|
Transmission
Line
|
|
40.
|
MPPKVVCL
|
Supply, Installation, Testing and Commissioning of New 11 KV Lines, LT Line on AB cable, Distribution Transformer Substation and Supporting works such as DPs, TPs, crossing etc. for separation of 11 KV mix Feeders & Mix DTRs under Revamped Reforms- based and Results-linked Distribution Sector (Package-17) in Seoni & Narsinghpur circle of MPPKVVCL, Jabalpur Company Area.
|
Transmission
Line
|
|
41.
|
MMRCL
|
Design and construction of Elevated metro viaduct of length 6.92 Km between Ch. (-) 657.182 m to Ch. (-) 7576.78 m in reach 2A of NMRP phase-2
|
Metro
|
|
42.
|
NHAI
|
Rehabilitation and Up gradation from 4 to 8 laning of Chandikhole - Paradip Section of NH-53 (Old NH - 5A) from Km.60.000 to Km.76.646 (Package-4) in the State of Odisha on HAM mode - 2 nd Call
|
NHAI
|
|
43.
|
Madhya Gujarat Vij Company Limited
|
MADHYA GUJARAT VIJ COMPANY LTD.: Revamped - Reforms - Based and Results - Linked Distribution Sector Scheme (RDSS) (Vadodara)
|
Transmission
Line
|
|
44.
|
Madhya Gujarat Vij Company Limited
|
MADHYA GUJARAT VIJ COMPANY LTD.:Full Turnkey Contract (Design, Supply and Installation) for Development of Distribution Infrastructure work for Loss reduction at Dist. Dahod under Revamped Reforms- Based and Result-linked Distribution Sector Scheme
|
Transmission
Line
|
|
45.
|
MMRCL
|
Construction of A) Six Elevated Metro Station viz. Pili Nadi to Lekha Nagar in Reach-2A, B) One Elevated and one At-Grade station viz. Eco park and Metro City in Reach-1A respectively. C) At-Grade section Formation earthwork, boundary wall and retaining wall between Ch. 19550 to Ch.20421.016 & Ch. 20498.516 to Ch. 21296.917, D) Elevated Metro track supporting structure for Ecopark Metro station between Ch.20421.016 to Ch. 20498.516 and E) Multi-Storied Building at Tulsi School Land (at Sitabuldi) of NMRP Phase-2
|
Metro
|
|
46.
|
Western
Railway
|
All civil engineering works (Earthwork, Blanketing, Retaining Wall / Boundary Wall/ Side Drain, Major Bridges, Minor Bridges and LHS/RUB, LCs, Construction of Station Buildings, Platform, Subways cover over Platforms, Staff Quarters, Passenger Amenities, Circulating Area, approach roads, Offices, Service Buildings, watering, Sanitation, protection works etc. and Supply of 50 mm Machine Crushed Stone Ballast, Complete track works including linking of Track works in connection with Gauge Conversion work between Petlad - Bhadran (22.50kms) of Vadodara Division on Western Railway.
|
Track Work
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
47.
|
Western
Railway
|
All civil engineering works (Earthwork, Blanketing, Retaining Wall/ Boundary Wall/ Side Drain, Major Bridges, Minor Bridges and LHS/RUB, LCs, Construction of Station Buildings, Platform, Subways cover over Platforms, Staff Quarters, Passenger Amenities, Circulating Area, approach roads, Offices, Service Buildings, watering, Sanitation, protection works etc. and Supply of 50 mm Machine Crushed Stone Ballast, Complete track works including linking of Track works in connection with Gauge Conversion work between Nadiad - Petlad (37.26kms) of Vadodara Division on Western Railway.
|
Track Work
|
|
48.
|
Central
Railway
|
Construction of 4 nos Tunnels (total Length 1.6km) with ballast less track, Earthwork in formation, Construction of Important Bridges (2nos), Major Bridges (1No), Minor Bridges (25nos) , Supply of Stone ballast, Track linking, side drain retaining wall etc. from Km. 831.8 to Km. 841.9 in Dharakoh Maramjhiri section in connection with third line.
|
Tunnels
|
|
49.
|
HPSEBL
|
Development of Distribution Infrastructure at SOUTH ZONE of Himachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works] NIT/RFB No: CE(MM)/RDSS-(P-03)/SOUTH ZONE
|
Transmission
Line
|
|
50.
|
HPSEBL
|
Development of Distribution Infrastructure at NORTH ZONE of Himachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works]
|
Transmission
Line
|
|
51.
|
MPMRCL
|
Part Design and Construction of Elevated Viaduct, Five (5) Elevated Metro Rail Stations (viz. Shaheed Bagh, Khajrana Chauraha, Bengali Chauraha, Patrakar Colony & Palasia Chauraha) and Ramp between Chainages 31+755 to 34+898.061 & 3+669.547 to 5+862 for Indore Metro Rail Project (Package IN-04)
|
Metro
|
|
52.
|
IR
SR
|
Varkala Sivagiri Railway station - Major upgradation / Redevelopement of Varkala Sivagiri Railway station in Kerala
|
Railway
Infrastructure
|
|
53.
|
MPPKVVCL
|
Supply, Installation, Testing and Commissioning of 11 KV Line associated works such as 11 KV Line Bifurcation, 11 KV Line Interconnection, 11 KV Line Conductor Augmentation, LT AB cabling augmentation and conversion of LT Bare conductor to AB cabling under Revamped Reforms-based and Results-linked Distribution Sector (Package-11) in Jabalpur (City), Jabalpur(O&M),Katni, Mandla, Dindori, Seoni, Chhindwara, Narsinghpur, Balaghat, Shahdol, Anuppur and Umariya Circles of MPPKVVCL, Jabalpur Company Area.
|
Transmission
Line
|
|
54.
|
MPPKVVCL
|
Supply, Installation, Testing and Commissioning of New 11 KV line for Bifurcation & Interconnection, Additional 11 KV Bay at 33/11 KV Sub-station, Augmentation of conductor of 33 KV & 11 KV Lines, Additional Distribution Transformer Substations with associate New 11 KV Lines, LT Line on AB cable, Conversion of bare LT line with AB Cable, Augmentation of LT AB Cable, Cover conductor for 11 KV Line Crossing Agriculture& Non Agriculture Feeder, 11 kv and 33 kv Bus Bar renovation other associated work, and Supporting works such as DPs, TPs, Crossing etc. in Jhabua O&M Division (LOT-12) under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme
|
Transmission
Line
|
|
55.
|
MPPKVVCL
|
Construction of 220KV & 132KV Transmission Lines and associated Feeder Bays on total Turnkey basis in Eastern MP
|
Transmission
Line
|
|
56.
|
MMRCL Pune Metro
|
Design and Construction of Elevated Viaduct of Length 4.519 Kms from CH: (-)1079.899m to CH: (-)5599.298m between PCMC and NIGDI (Bhakti Shakti) on the North-South Corridor of Pune Metro Rail Project- Reach1 - Extension.
|
Metro
|
|
57.
|
RRVPNL
|
Supply & ETC of 132/33kV Grid Sub-stations alongwith associated Lines & Bays
|
Transmission
Line
|
|
58.
|
Central
Railway
|
Signalling and Telecommunication work for provision of Automatic block signaling on Khapri-Sewagram Section of Nagpur Division. Tender No. 55-2023-GSU-AUTO-KRISEGM
|
Signalling
|
|
59.
|
IR
SCR
|
Engineering, Procurement and Construction (EPC) Tender for "Proposed Doubling of Track between Ankai station (Excluding) at Km 16.00 (Ch 16000) & Karanjgaon Station (Excluding) at Km 69.01(Ch 69010) [i.e. (53.01 km)] including Electrification and Signaling works in connection with Aurangabad-Ankai Doubling Project in Nanded Division of South Central Railway".
|
Track Work
|
|
60.
|
IR
SR
|
Redevelopment of Thiruvananthapuram Central Railway Station (JV with KRDCL)
|
Railway
Infrastructure
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
61.
|
IR
Southern
Railway
|
Provision of Automatic Block Signaling system in Jolarpettai Junction to Erode Junction of Salem Division in Southern Railway.
|
Signalling
|
|
62.
|
IR
Eastern
Railway
|
Construction of Sitarampur bye pass line under Asansol Division of Eastern Railway.
|
Track Work
|
|
63.
|
IR
South East
Central
Railway
|
Provision of Auto Signalling with Electronic Interlocking (OFC Based) between Champa- Saragaon-Baraduar-Sakti section with alteration in existing Electronic Interlocking & Supply, Installation, Testing, Commissioning of new Electronic Interlocking, MSDAC & IPS etc., execution of all indoor & outdoor works & construction and Electrification of the huts etc. in Champa-Sakti Section of Bilaspur Division of S.E.C. Railway.
|
Signalling
|
|
64.
|
NMRCL
|
Construction of 6 Nos Elevated Metro Stations (Cantonment, Kamptee Police Station, Kamptee Municipal Council, Dragon Palace, Golf Club And Kanhan River Metro Station) Between Ch.-7576.78mm To Ch-13457.76m In Reach 2b of NMRP Phase 2
|
Metro
|
|
65.
|
IR
North
Central
Railway
|
Provision of EI based Automatic Signaling with continuous track circuiting and other Associated works along with suitable indoor alterations in Electronic interlocking / RRI/PI stations enroute in Dhaulpur-Gwalior Section of Jhansi division of North Central Railway
|
Signalling
|
|
66.
|
NTPC
|
PEA contract for execution of Balance Civil & HM works of Barrage Complex including part HRT package of Rammam Hydro Electric Project Stage-III (3x40 MW).
|
Infrastructure
|
|
67.
|
Southern
Railway
|
Provision of Automatic Signalling on Ernakulam JN(ERS) - Vallattol Nagar (VTK) Section on B-Route of Thiruvananthapuram Division in Southern Railway
|
Signalling
|
|
68.
|
Central
Railway
|
OHE modification work for Up-gradation of existing 1 x 25 kV Electric Traction System to 2 x 25 kV AT Feeding System in Amla-Nagpur Section in Nagpur division of Central Railway to meet 3000 MT loading target.
|
Electrical
|
|
69.
|
Bangalore
Metro
|
Engineering, Supply, Erection, Testing and Commissioning of 33 Kv Distribution, 750v Dc Third Rail Traction Electrification Including Traction Substations, Auxiliary Substations and Scada System for Phase-2a & Phase-2b
|
Metro
|
|
70.
|
East Coast Railway
|
Provision of Automatic Block Signaling system with dual MSDAC and alteration in existing EI/PI/RRI stations in the section of Jakhapura-Nergundi, Khurda Road- Bhusundpur & Bhusundpur-Golanthra over Khurda Road Division of East Coast Railway. Tender No. SNTPBBS-032024-JKPR-GTA
|
Signalling
|
|
71.
|
SER
|
Design, Supply, Erection, Testing & Commissioning of 132 KV Traction Substation, Sectioning post (SPs), and Sub sectioning post (SSPs) in 2x25KV System on Rajkhaswan- Nayagarh-Bolani section of Chakradharpur division of South Eastern Railway to meet 3000MT loading target on EPC mode
|
Electrical
|
|
72.
|
Central
Railway
|
OHE modification work for Up-gradation of existing 1 x 25 kV Electric Traction System to 2 x 25 kV AT Feeding System in Wardha-Ballarshah Section in Nagpur division of Central Railway to meet 3000 MT loading target
|
Electrical
|
|
73.
|
Central
Railway
|
Design, Supply, Erection, Testing & Commissioning of 132 KV Traction Substation Sectioning post (SPs) and Sub sectioning post (SSPs) in 2x25KV System on Kharagpur - Bhadrak section of Kharagpur division of South Eastern Railway to meet 3000MT
|
Electrical
|
|
74.
|
Himachal
Central
zone
|
Development of Distribution Infrastructure at CENTRAL ZONE of Himachal Pradesh under the Revamped Reforms-based and Results-linked, Distribution Sector Scheme [Loss Reduction Works
|
Transmission
Line
|
|
75.
|
Southern
Railway
|
Provision of MSDAC with existing DCTC at Stations (To serve as Dual detection) and replacing balance AFTCs in MAS- GDR & MSB-TBM automatic block signalling sections of Chennai Division in Southern Railway.
|
Signalling
|
|
76.
|
ECR
|
Design, Supply, Erection, Testing and Commissioning of 2x25KV feeder line along the track with 25KV OHE modification works to meet 3000 MT loading target for UP & DN line of Garwa Road -Mahadiya Section of Dhanbad Division under E.C. Railway (Total 229/458 RKM/TKM).
|
Electrical
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
77.
|
East Coast Railway
|
3rd& 4th line between Jarapada & Talcher Road and Construction of New line between Angul-Balram (MCRL Inner Corridor Phase-I Doubling 14 Kms).: Execution of balance earthwork in formation, minor bridges, major bridges, P.way linking works, supply of ballast, S&T Buildings, Level Crossing and other Misc. works between Jarapada and Talcher Road excluding station yards in connection with 3rd& 4th line of Jarapada- Budhapank Project and between Angul & Balram including yards of MCRL Inner Corridor Phase-I Doubling
|
Track Work
|
|
78.
|
NMRCL
|
Construction Of (A) Elevated Metro Stations Seven Nos In Reach 3a, Namely (1) Hingna Mount View, (2) Rajiv Nagar, (3) Wanadongri,(4) Apmc,(5)Raipur,(6) Hingna Bus Station (7) Hingna,(B) Elevated Metro Stations Three Nos In Reach 4a, Namely (1) Pardi,(2) Kapsi Khurd (3)Transport Nagar of NMRP Phase-2.
|
Metro
|
|
79.
|
ECR
|
Design, Supply, Erection, Testing & Commissioning of Traction Sub Stations with associated Switching Posts for upgradation work of electric traction system from 1X25 to 2 X 25 KV AT feeding system in Gomoh - Patratu Section of Dhanbad Division of East Central Railway
|
Electrical
|
|
80.
|
South
Central
Railway
|
Engineering, Procurement and Construction (EPC) contract Agreement for Doubling of Track between Parbhani to Parli stations (58.06Kms) (excluding Gangakhed yard from km 292.075 to km 298.85 =6.775 Km) including Electrification & Signaling works in connection with Parbhani -Parli doubling project of South Central Railway in the state of Maharashtra."
|
Track Work
|
|
81.
|
ER
|
Earthwork in cutting and filling, blanketing, construction of minor bridges, major bridges, RUB, ROB, retaining wall, level crossing, side drain, catch water drain, P.way work and other ancillary works from IR Ch. 205.000 km to 260.2 Km between Kalipahari (inc.) to Pradhankhuta (exc.) in connection with construction of multi tracking Railway BG line.
|
Track Work
|
|
82.
|
BSNL
|
BHARAT SANCHAR NIGAM LIMITED (A Government of India Enterprise)-Bid Document for Development (Creation, Upgradation and Operation & Maintenance) of Middle mile network of BharatNet on Design Build Operate and Maintain (DBOM) Model. Package No. -1 to 8.
OPEX (Operation & Maintenance) for 10 years for Pkg 3.
|
BharatNet
|
|
83.
|
BSNL
|
BHARAT SANCHAR NIGAM LIMITED (A Government of India Enterprise)-Bid Document for Development (Creation, Upgradation and Operation & Maintenance) of Middle mile network of BharatNet on Design Build Operate and Maintain (DBOM) Model. Package No. -1 to 8.
OPEX (Operation & Maintenance) for 10 years for Pkg 6.
|
BharatNet
|
|
84.
|
KRIDE
|
Package C-4A: Construction of Nine (9 Nos.) Stations i.e. Elevated (1 No.) and At-Grade (8 Nos.) BSRP Stations of Corridor-4A at Heelalige, Singena Agrahara, Huskur, Ambedkar Nagar, Carmelaram, Bellandur, Marathahalli, Doddanakundi, Kaggadasapura including Civil, Structural, Entry / Exit Structure, Steel FOB, Roof Structures, PEB works Architectural finishes and E&M Works and Detailed Design & Engineering (DDC) with all associated works for Bengaluru Suburban Rail Project" (BSRP)"
|
Metro
|
|
85.
|
SCR
|
SCR Construction Organization: Engineering Procurement Construction (EPC) Contract of Doubling of Track between Navipet station (Excl) From Km 446.900 to Indalvai Station (Incl) Km 482.900 (33.70 km), {Excluding Nizamabad Yard from Km 458.825 to 461.125 (i.e.) 2.3Km} including Electrification & Signaling works in of South-Central Railway in connection with Mudkhed-Medchal Doubling Project in the State of Telangana.
|
Track Work
|
|
86.
|
Punjab
RDSS
|
Development of Distribution Infrastructure Work for Package-3 Central Zone for Execution of Ht/Lt Infrastructure Loss Reduction Works Under Reforms- Based and Results-Linked, Revamped Distribution Sector Scheme (RDSS) In the State of Punjab.
|
Electrical
|
|
87.
|
CR
|
Design, Supply, Erection, Testing & Commissioning of 132/55 KV Traction Substation, Sectioning post (SPs) and Sub sectioning post (SSPs) in 2 x 25 KV Traction System (Scott Connected Transformer) of Bhusaval - Khandwa Sections of Central Railway, to meet 3000 MT loading target on EPC mode.
|
Electrical
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
88.
|
East Coast Railway
|
Koraput-Singapur Road Doubling Project: "Execution of 27 Nos of Major Bridges i.e. (22 Nos of Major Bridges & 5 Nos of ROBs) and earth work in formation of approaches, protection works and other connected miscellaneous works between Tikiri and Bhalumaska stations in connection with Koraput-Singapur Road Doubling Project of Waltair Divison, East Coast Railway
|
Track Work
|
|
89.
|
SER
|
Design, Supply, Erection, Testing and Commissioning for upgradation of Electric traction system from 1 x 25 KV to 2 x 25 KV traction system for Kharagpur (Excl.) -Tatanagar (Incl.) section of Kharagpur/Chakradharpur division of South Eastern Railway to meet 3000 MT loading target.
|
Electrical
|
|
90.
|
SWR
|
Engineering, Procurement and Construction (EPC) for Design, Supply, Erection, Testing, Commissioning of 2x25 KV OHE & PSI System (TSSS, SPS & SSPS) Including Electrical General Services, Engineering & Telecommunication Works Between Rayadurga (Excl.) (Ch:205/463) To Pavagada (Incl.) (Ch:106/000) of TK-RDG Section (99.463 rkm/114.145 tkm)
|
Electrical
|
|
91.
|
NHAI
|
Construction of six lane connectivity to Visakhapatnam Port Road from Km 0.000 (Sabbavaram bypass of Anakapalli - Anandapuram corridor) to Km 12.660 (Sheela nagar junction) of NH 516C on Hybrid Annuity Mode in the State of Andhra Pradesh under NH(O)
|
Road
|
3.7.2.2 The list of projects 13 projects awarded to RVNL through Competitive Bidding in 2025-26 and under execution is as under:
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
1
|
South
Western
Railway
|
Survey, design, supply, installation, testing and commissioning of KAVACH equipment and other associated works over 790 RKM of Hubballi & Mysuru Divisions of South Western Railway.
|
Signalling
|
|
2
|
CR
|
OHE Modification Work for Up-gradation of existing 1x25 KV Electric Traction System to 2x25 KV AT Feeding System in Itarsi - Amla Section in Nagpur Division of Central Railway to meet 3000 MT Loading Target.
|
Electrical
|
|
3
|
DMRC
|
Contract D2C-02; Part Design and Construction of Viaduct of Length 7.298 kms. from Chainage 1202.782 m to Chainage 8501.25 m including seven (07) stations (Only platforms) namely Pushp Vihar, Saket District Court, Pushpa Bhawan, Chirag Delhi, GK- 1, Andrews Ganj and Lajpat Nagar including Pre-Engineered Building Structure in all stations of Lajpat Nagar to Saket G Block Corridor of Delhi MRTS Phase-IV Project.
|
Metro
|
|
4
|
SR
|
Upgradation work of Electric traction system from 1x25 kV to 2x25 kV traction system for Salem Jn. (SA) - Podanur Jn. (PTJ) & Irugur (IGU) - Coimbatore Jn. (CBE) - Podanur Jn.(PTJ) section of Salem division of Southern Railway to meet 3000 MT loading target.
|
Electrical
|
|
5
|
SCR
|
Design, Supply, Erection, Testing and Commissioning for OHE upgradation of existing 1X25kV system to 2X25kV AT feeding system with feeder and earthing works in Duvvada- Rajahmundry & Samalkot - Kakinada Port section of Vijayawada Division under South Central Railway, Total 195.5 RKM/ 391 TKM.
|
Electrical
|
|
6
|
SR
|
Design, Supply, Erection, Testing & Commissioning of Traction Sub Stations (Scott- Connected) Inclusive of Power Quality Compensating Equipment with Associated Switching Posts (SP/SSP) for 2x25 kV AT Feeding System and SCADA & Automatic Fault Locator (AFL) In Jolarpettai Jn. - Salem Jn. (JTJ-SA) Section of Salem Division of Southern Railway In Connection With Mission 3000MT Loading Target.
|
Electrical
|
|
7
|
SECR
(IRCON)
|
Supply of various signalling, telecommunications and EIMWB materials; Installation, Testing and Commissioning of Distributed/Centralised Electronic Interlocking (El) Installations at 10 new stations, viz., Surakachhar, Block Cabin, Katghora Road, Bhingra, Putuwa, Matin, Sendurgarh, Putipakhana, Dhangawan and Bhadi stations; 06 new IBSs in the Bhingra-Putuwa, Putuwa-Matin, Sendurgarh-Putipakhana, Putipakhana-Bhadi, BhadiDhangawan & Dhangawan-Pendra Road block sections; Installation, Testing and Commissioning of New Section Control System with Headquarters and Wayside Train Control Communication Equipment I System in the Gevra Road - Pendra Road section; Installation, Testing and commissioning of new Telephone Exchange and EIMWBs at appropriate location(s) through execution of various signalling & telecommunications works; alterations I modifications in the existing Panel Interlocking Installation at Kusmunda Block Station (KBS) yard and the existing Electronic Interlocking Installation at East Cabin of the SECL SILO Siding (KMKA) yard including other miscellaneous works.
|
Signalling
|
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
8
|
SR
|
Provision of Video Surveillance System (VSS) at 441 D & E Category Stations along with Augmentation at 43 Stations (Categories A1, A, B, and C) over Southern Railway".
|
Signalling
|
|
9
|
NER
|
Construction of substructure of Important Bridge No. 50 (14x61.0 m) with Double D type well foundation for double line with RDSO 25 T Axel loading standard over river Gandak between Paniyahwa - Valmikinagar station in connection with Doubling work between Gorakhpur Cantt-Valmikinagar section of North Eastern Railway.
|
Civil
|
|
10
|
ECoR
|
Setting up of Wagon POH Workshop of 200 Nos. Capacity at Kantabanji.
|
WKSP
|
|
11
|
SCR
|
Design, Supply, Erection, Testing and Commissioning for OHE up gradation of existing 1X25kV system to 2X25kV AT feeding system with feeder and earthing works in Ramgundam(RDM) - Kazipet(KZJ) section of Secunderabad Division under South Central Railway, Total 92 RKM/ 276 TKM.
|
Electrical
|
|
12
|
CR
|
Design, Supply, Erection, Testing & Commissioning of 220/132/55 KV Traction Substation, Sectioning post (SPs) and Sub sectioning post (SSPs) in 2 x 25 KV Traction System (Scott Connected Transformer) of Daund - Solapur Sections of Central Railway, to meet 3000 MT loading target on EPC mode
|
Electrical
|
|
13
|
NR
|
Design and Construction of New Rail Cum Road Bridge No. 11 over river Ganga, 50 Meters downstream of the existing old Malviya Bridge near Kashi Railway Station, including sub structure and super structure of the Bridge (8 X 108.5 m + 2 X 103.3 m Open Web Steel Girder) for four line tracks on lower deck and six lane Road on upper deck, including Railway and Road approaches as per GAD along with associated OHE Works and General Electric works in Lucknow Division of Northern Railway at Varanasi, Uttar Pradesh, India
|
Civil
|
3.7.2.3 The list of Non-Railway Nomination projects are under execution is an under:
|
S.
No.
|
Agency/ Client
|
Name of Project
|
Plan Head
|
|
1
|
AAI
|
Construction of Sub-ways / Underpass to connect operational area to the Airport Authority of India residential colony in Kolkata
|
Civil
|
|
2
|
VPA
|
Construction of internal flyovers to enhance the smooth evacuation of cargo and eliminate the eleven (11) level crossings that currently hindering the free flow of traffic at VPA
|
Civil
|
|
3
|
Uzbakisthan
|
Supply, testing and commissioning of Solar PBcell for 250 K watt Electricity_ Uzbakisthan
|
Electrical
|
|
4
|
Tabarjal
|
Supply, testing and commissioning of Solar PBcell for 400 K watt Electricity_Tabarjal
|
Electrical
|
|
5
|
NMDC
|
Construction of 15 nos Type III (600 Units), 01 No Type IV (40 Units), 01 No Type V (30 Units) Residential Towers, 01 HOP Bungalow and shopping complex in existing NMDC Bacheli Township, Chhattisgarh
|
Civil
|
|
6
|
NMDC
|
Development of new township near Arvind College area and construction of residential towers in existing NMDC Kirandul Township, Chhattisgarh
|
Civil
|
|
7
|
NMDC
|
Construction of Type-IV Residential Towers, Club house in NMDC Kirandul Township at Arvind College Area, Chhattisgarh
|
Civil
|
|
8
|
NMDC
|
Construction of Residential Towers at Bacheli Complex under Capacity expansion of Bailadilla Iron Ore Deposit-10/11A NMDC Bacheli, Chhattisgarh.
|
Civil
|
|
9
|
NMDC
|
Construction of Residential Towers at Bacheli under Capacity expansion of Bailadila Iron Ore Deposit-5 NMDC Bacheli Township, Chhattisgarh
|
Civil
|
|
10
|
NMDC
|
Refurbishment of Permanent Way of NMDC Sidings & Mobile Equipment Tracks including Maintenance at Kirandul & Bacheli, Chhattisgarh
|
Civil
|
3.8 Major Projects awarded through Bidding:
3.8.1 Indore Metro Project:
Rail Vikas Nigam Limited (RVNL) has been awarded three major packages (IN02, IN03 & IN04) of the yellow line of the project.
Package 02- (7 no. of Elevated Metro Stations)
Package 03- (10.9 Km Viaduct & 9 no. of Elevated Metro Stations)
Package 04 with JV - (1.3 km Viaduct & 2 no. of Elevated Metro Stations)
ACHIEVEMENTS: • Commercial operations for 5.9 km viaduct and 5 elevated metro station are in progress since June 2025.
• The three-day CMRS visit from 15.03.2026 to 17.03.2026, covering SC-02 to Malviya Nagar station, has been successfully completed, including speed trial and inspection of 6 km viaduct with 11 stations of the Indore Metro Priority Corridor (Yellow Line).
• Along with the earlier commissioned 5.9 km viaduct and 5 stations by RVNL, a total of 10.9 km viaduct and 16 stations (Pkg-02 & 03) secured through bidding stand completed.
• Commercial operation for remaining stretch is proposed in June 2026.
• Package IN-04: Works are currently in progress for Viaduct section and two nos. of elevated stations.
3.8.2 Underground Metro Projects at Chennai (CMRL)
RVNL has won 3 contracts on bidding with Chennai Metro Rail Limited (CMRL) as part of it's massive Phase -II expansion in the year 2023 comprising Construction of 16 Nos of underground stations spread over 3 contract packages.
|
Package
|
Stations
|
Status
|
|
UG03
|
Kilpauk, Sterling Road, Nungambakkam, Gemini (Anna Flyover), 1000 Lights, Chetpet, Royapettah - 7 Stations
|
Diaphragm wall & slab works in progress. Utility diversion works nearing completion.
|
|
UG04
|
RK Salai, Thirumayilai (C3 & C4), Mandaiveli, Greenways Road, Adyar Junction - 5 Stations
|
Diaphragm wall & slab works in progress. Utility diversion works nearing completion.
|
|
UG05
|
Adyar Depot, Indira Nagar, Tiruvanmiyur, Taramani Road Junction - 4 Stations
|
Diaphragm wall & Utility diversion works in progress.
|
|
16 stations
|
All the 3 projects are progressing as per the timelines. The project includes some of the deepest stations on the Chennai metro network and are being executed in the heart of the city. The projects on completion are destined to transform the city of Chennai the significant contribution of RVNL in shaping the urban infrastructure will be recorded & recognized as a Nation building exercise.
UG-04 - RK SALAI STATION (North shaft Roof slab casting in progress)
|
The List of machineries mobilized for each package as on date is as follows:
|
|
Package
|
Min Requirement
|
Actual Mobilization
|
|
| |
Trench Cutter GRAB
|
Trench Cutter
|
GRAB
|
Piling Rig
|
|
UG - 3
|
3 3
|
7
|
2
|
8
|
|
UG - 4
|
4 1
|
5
|
3
|
3
|
|
UG - 5
|
2 2
|
2
|
2
|
3
|
|
Total
|
9 6
|
15
|
7
|
14
|
3.8.3 Nagpur Metro Projects - Phase - II.
Project -1: Design and Construction of Elevated Metro Viaduct of length 6.92 km.
Project Brief: DOC - 06.10.23 with original completion date as 05-04.26 i.e. 30 Months.
(Approved EOT Date is 30.06.27).
Achievements:
1. 3.5km has been completed out of 6.93 Km.
2. Package involves CLC Construction work of 210m, Its Hammer Head construction work is 50% completed.
3. Physical (%) Completion - 71%
Project -2: Construction of 6 Nos of Elevated Metro Station - Reach-2A & 2 Nos of At-Grade Stations-Reach1A with Track Supporting Structures.
Project Brief: DOC - 06.10.23 with original completion date as 05-04.26 i.e. 30 Months.
(Reach2A- Approved EOT Date is 30.09.27).
Achievements:
Reach-2A Station - RCC Work -52% completed. Physical (%) Completion - 49%.
Reach-1A Station - RCC Work -98% completed. Finishing - 65% completed.
Physical (%) Completion - 85%.
Project -3: Construction of 6 Nos of Elevated Metro Stations - Reach-2B
Project Brief: DOC - 09.07.24 with original completion date as 04-01.27 i.e. 30 Months.
Achievements:
1. RCC Work - 34% completed.
2. Physical (%) Completion - 29%.
Project -4: Construction of 7 Nos of Elevated Metro Stations - Reach-3A & 3 Nos in Reach 4A.
Project Brief: DOC - 16.12.24 with original completion date as 14-06.27 i.e 30 Months project duration.
Achievements:
1. RCC Work - 17% completed.
2. Physical (%) Completion - 15%.
3.8.4 Kakinada 4 - Lane Project of NHAI
Under Bharatmala pariyojana, RVNL PlU/Waltair is executing the 12.25km 4-lane highway from Samarlakota to Achampeta junction as a part of port connectivity road from Kakinada port to NH-16 (Kolkata-Chennai). Completion of this project will enhance logistic efficiency and reduce logistics costs of freight movements.
|
LOA Issued
|
29-09-2022
|
|
Agreement Signed Date
|
01-05-2023
|
|
Appointed Date
|
17-08-2023
|
|
Physical Progress
|
93%
|
3.8.5 Development of Kharicut Canal, Ahmedabad Municipal Corporation area Package 2 & 3
Kharicut canal is 137 years old canal system catering 10200 ha command area for disposal of rain and storm water from upstream catchment area between Sabarmati and Khari rivers and also used for irrigation purpose. Approximate 23 Km length of Kharicut canal which was passing through agricultural land and surrounding villages of Ahmedabad City is now passing through the dense eastern part of Ahmedabad city.
The work of development of the Kharicut Canal was awarded by AMC on 19.10.2022 & RVNL's scope of work covers a total length of 5.1 km, falling under Package 2 & 3, from chainage 2500 to 7600. The primary objective of this project is to improve the environmental and sanitary conditions for residents living along the canal by eliminating unhygienic and foul-smelling surroundings, thereby reducing the risk of diseases. Additionally, the canal alignment has been integrated with a four-lane road, aimed at easing traffic congestion and improving urban mobility. The work has been successfully completed and the Kharicut Canal development projects was inaugurated by Hon'ble Prime Minister Narendra Modi on 31.03.2026
3.8.6 Manufacturing of 120 Nos. Trainsets (VANDE BHARAT)
The Vande Bharat Trainset Project is a major Indian Railways modernization initiative aimed at manufacturing 120 semi-high-speed electric trainsets comprising 1,920 cars, designed to operate at a speed of 160 kmph. The project involves an estimated D14,400 crore for manufacturing and around D20,000 crore for maintenance over a 35-year period, ensuring complete life-cycle support from design and production to long¬ term depot maintenance.
The project is being executed by KINET Railway Solutions Limited, a SPV created for this purpose, with shareholding of LES - 40%, MWM - 35%, and RVNL - 25%. MWM
and LES are responsible for the core technical design and manufacturing support, while RVNL is handling key activities such as training, simulator deployment, and upgradation of manufacturing workshop and maintenance depots.
Manufacturing activities for the first prototype are being progressively scaled up at the fully upgraded MRCF Latur facility. The final painting work of DTC-1 has been completed, while in DTC-2, core welding work has been completed, and painting along with other finishing activities are currently in progress. For DTC-3, manufacturing work is also under progress, indicating significant advancement in trainset production.
Long-term maintenance of the trainsets will be supported through three major depots: Jodhpur, targeted for completion by February 2027; Bengaluru contract awarded on 27.4.2026 with 30-month completion period from the date of award of contract; and Bijwasan,
where the tender is scheduled to open on 30.6.2026. Each depot will be equipped with all modern facilities to maintain approximately 40 to 50 trainsets.
These fully air-conditioned, faster-accelerating Vande Bharat trainsets are intended to gradually replace conventional rolling stock and enhance indigenous manufacturing capabilities. With modern features such as premium interiors, automatic doors, CCTV surveillance, bio-vacuum toilets, and Divyangjan-friendly accessibility, the project is expected to significantly improve passenger comfort, safety, and overall travel experience and usher in an era of superior human transport over Indian Railways.
3.8.7 First overseas project in Maldives
RVNL bagged the first offshore order for development of a port and construction of allied infrastructure in Maldives, i.e. for development of UTF (Uthuru Thila Falhu- Island) Harbour Project. This is a strategic project of Government of India. The agreement was signed in January 2023.
The work has progressed well, with overall physical progress is 80% which includes 96% progress of marine works & 60% in Landside works.
3.8.8 Araria-Thakurganj-Galgalia New BG Line Electrification Project (110 RKM/129 TKM) represents a landmark infrastructure initiative of strategic importance for NFR, creating a vital alternate Katihar-Siliguri corridor and significantly strengthening rail connectivity to Northeast India and the border regions adjoining Nepal. The project involved comprehensive 25 kV AC railway electrification infrastructure, including Overhead Equipment, Traction Substations, SP/SSP installations, and SCADA systems, thereby enabling efficient, reliable, and environment-friendly electric traction on this important route. One of the most notable benefits of the project is the reduction in the New Jalpaiguri-Delhi route distance from approximately 1,650 km to 1,409 km, resulting in a saving of about 241 km. This will translate into reduced travel time, lower operating costs, improved asset utilization, enhanced throughput, and greater operational flexibility for passenger as well as freight services. The physical progress achieved under the project was substantial, with around 2,790 OHE foundations cast, 2,884 masts and structures erected, 2,821 bracket assemblies installed, and 153 OHE wiring shots executed, reflecting the scale, speed, and quality of execution.
The successful completion of the project was achieved despite formidable challenges such as shortage of skilled manpower and specialized equipment, high embankments, flood-prone terrain, sandy soil conditions, heavy rainfall, theft-prone locations, restricted site access due to absence of level crossings, dependence on other executing agencies, and uncertainties in traffic block availability. These constraints were effectively addressed through proactive planning, deployment of additional UTVs, crane, operators, and safety supervisors, engagement of multiple subcontractors for parallel execution, enhanced security through retired RPF personnel, direct procurement of OHE conductors, and round-the-clock working at critical locations. The project was commissioned in phases, with Thakurganj (Excl.)- Bibiganj (Incl.) (42 RKM/47 TKM) commissioned on 30.06.2025, followed by Bibiganj (Excl.)-Araria (Excl.) and Araria Court (Excl.) (68 RKM/82 TKM) on 15.10.2025, while the Kaliaganj 132/25 kV TSS was commissioned on 23.12.2025. Completion of this strategically significant project ahead of the contractual schedule demonstrates RVNL's execution capability, project management excellence, and commitment to nation-building. It is also a milestone achievement as RVNL's first Railway Electrification project executed under the BD mode, setting a strong benchmark for future BD-mode electrification works.
3.9 Strategic Railway Projects by RVNL
3.9.1 RISHIKESH-KARANPRAYAG NEW RAIL LINK PROJECT - 125 KM
This transformative project in Uttarakhand is being executed by RVNL. It will connect the state's remote hinterlands directly by rail, marking a new chapter in
regional connectivity and development. The project spans 125 kms, and the route is charted through the challenging Himalayan terrain. The project comprises 12 new stations 28 tunnels with a cumulative tunnel length of 213 kms. and 19 major rail bridges, making it one of the most challenging projects currently underway in India. This line may also serve as the main feeder route for any future Chardham connectivity.
The first block section, 5.7 km stretch between Virbhadra and Yog Nagari Rishikesh was successfully completed and commissioned in March 2020. Out of the total 213 kms of tunnel excavation planned, 205.82 km have already been completed along with 146.76 km of final lining. 8 out of the 19 major rail bridges have been completed, ensuring vital connectivity across difficult river crossings and valleys. In addition, Three key road bridges have been constructed to facilitate access to work sites and future stations. 40 Breakthroughs out of 46 drives have been successfully achieved.
The New Line is expected to be a catalyst for the socio economic development of the region and will considerably reduce travel time. The Breakthrough of 14.57-km- long tunnel no 8 between Devprayag and Janasu was witnessed by Hon'ble Railway Minister. This is the India's longest transportation tunnel.
3.9.2 BHANUPALI-BILASPUR-BERI NEW LINE
The 63Km long Railway line passes through the challenging hill terrain of the lower Himalayas with a total route tunneling of 25.9 Km. The proposed electrified BG rail line shall enable regional development through the connectivity of Himachal Pradesh with the national railway network, and will act as a gateway to connect with the international borders towards Leh for strategic purposes.
3.9.3 Kolkata Metro Projects:
3.9.3.1 Indian Railways transferred the works of four major projects for extension of
Kolkata Metro to RVNL in March 2010 viz.
• Joka-BBD Bag via Majerhat (16.72 km)
• Dum Dum Airport-New Garia via Rajarhat (32 km)
• Baranagar-Barrackpore& Dakshineswar (14.5 km)
• Noapara (Ex.)-Baranagar (2.6 km)
3.9.3.2 Thereon RVNL was entrusted to build Metro corridors of about 65 km in Kolkata without any survey of underground utilities and without any DPR (Detailed Project Report). The issues like removal of encroachments and relocation of utilities along with delay in availability of traffic diversion have affected the execution. RVNL has taken all possible action for implementation and early commissioning of Metro projects for larger interest of people of Kolkata.
3.9.3.3 The foundation stone for Joka-BBD Bag project was laid by Her Excellency, President of India on 22.01.2010. Subsequently, 2 packages for viaduct and 2 packages for stations were awarded in December 2010 and April 2012 respectively. This entire Metro corridor has been planned in 3 phases i.e. in 1st phase from Joka to Majerhat elevated section and in the 2nd phase from Majerhat to Mominpur in 3rd phase from Mominpur to Esplanade station as underground section. Originally sanctioned as elevated section but Material Modification is sanctioned by Ministry of Railways for underground system from Mominpur to Esplanade. For construction of Mominpur station, working permission from Army HQ has been received only on 20.03.2023 and work going on full swing.
3.9.4.4 Joka - Esplanade Metro Corridor
In the Metro corridor from Joka to Majerhat, from Joka to Taratala (Phase-I) 6.50 Km has been inaugurated by Hon'ble Prime Minister on 30.12.2022 & commercial services started by Metro Railway on 02.01.2023. Another phase of 1.25 Km from Taratala to Majerhat has been inaugurated by Hon'ble Prime Minister on 06.03.2024 & commercial services started by Metro Railway has been commenced from 15.03.2024. The station over yard at Majerhat is on three layers. Beyond Majerhat, the Joka to Majerhat Metro Corridor is being extended upto Esplanade going underground from Mominpore ramp. The Works contract for the underground section has been awarded and the works of underground portion has been started. Working permission has accorded after Hon'ble High Court/ Kolkata's clearance for execution in Defence land in the Maidan area for the public interest of Kolkata. The NOC from Victoria Memorial Trust has been received recently to go ahead with underground station near Victoria Memorial.
Since this Metro stretch is a standalone system, a Maintenance Depot has been developed in Joka which is under operation. Earlier, due to non-availability of land (24.48 hectare), the tender for the depot was discharged twice, once in February 2013 and again on October 2017.
The commissioning is planned in 3 phases i.e (a)Ph-I-Joka- Taratala, (b)Ph-II-Taratala-Majerhat, (c) Ph-III- Majerhat- Esplanade. After starting of commercial services of 1st & 2nd phase commissioning the outskirt population of Kolkata has been connected to Kolkata which is a great relief for the people residing away from Kolkata but normally come to Kolkata on daily basis doing a tough journey every day. On Phase 3 work is in progress, for tunnelling both TBMs namely DURGA and DIVYA have commenced mining towards Victoria, progress of mining is 1594 m and 1264 m, respectively. Further, Station Construction activities are in progress at Victoria and Park Street Stations, while works at Khidderpore and Esplanade Stations are yet to commence. At Victoria Station, construction of the D-Wall, piles, and top slab has been completed, and the concourse
slab is currently in progress. At Park Street Station, D-Wall construction is in progress. Critical issues affecting progress are shifting of B. C. Roy Market, transfer of land from the Consulate General of Nepal, and relocation of the PWD office.
3.9.4.5 New Garia-Airport Metro Corridor
In the section of New Garia to Rabindra Tirtha of Dum Dum Airport-New Garia project, initially 4 packages of Viaduct were awarded on 21.10.2011. About 20 km viaduct has been completed. The contracts for 21 stations (3 packages) were awarded on 05.03.2014. Out of 21 stations, station land for Technopolis Metro station is now handed over. The project got delayed because of issues relating to land acquisition, traffic diversion, utility diversion and other permission over busy EM Bypass road. Further, change of alignment proposed by State Government where unauthorized buildings were constructed even after the Gazette Notification for Metro construction, and other impediments like shifting of markets, traffic guard, raising of 220 KV overhead line, removal of encroachments, etc. slowed down the progress of work. Substantial part of these impediments have been either removed and the balance are on the way of being removed. The alignment from City Centre-II to Airport is now approved by State Government after long persuasion and contract for construction of Metro beyond Titumir to Airport has been awarded on 18.01.2021, The work is under progress. In this section the commissioning was planned in 3 phases phases earlier i.e (a) Ph-I-New Garia-Hemanta Mukhopadhyay, (b)Ph-II-Hemanta Mukhopadhyay to Salt Lake Sector-V and (c) Ph-III- Salt Lake Sector-V to Airport. Due to unavailable work front in various stretches of the corridor and considering commissioning point of view the phases were revised i.e. (a) Ph-I-New Garia-Hemanta Mukhopadhyay, (b)Ph-II-Hemanta Mukhopadhyay to Beleghata, (c) Ph-III Beleghata to Salt Lake Sector-V and (d) Ph-IV- Salt Lake Sector-V to City Centre 2 and (e)Ph-V City Centre 2 to Airport.
Now in present scenario, (a) Ph-I-New Garia-Hemanta Mukhopadhyay (5.4 Km) commercial run has been started from 15.03.2024 after being dedicated to the nation by the Hon'ble Prime Minister on 06.03.2024, (b) Ph-II-Hemanta Mukhopadhyay to Beleghata (4.46 Km) commercial run has been started from 25.08.2025 after being dedicated to the nation by the Hon'ble Prime Minister on 22.08.2025. , (c) Ph-III Beleghata to Salt Lake Sector-V was planned for commission in Dec'2026, however due to non-availability of traffic diversion block between Belaghata to Gour Kishore Ghosh stations, work of launching of viaduct is held up since Feb 2025 to mid of May 2026. Now work has been started again and it will take 5-6 months to complete the remaining work. Balance 02 phase i.e. (d) Ph-IV- Salt Lake Sector-V to City Centre 2 has been planned for commission in Jun'2027 and (e)Ph-V City Centre 2 to Airport are planned for commission upto Dec'2027.
3.9.4.6 Noapara - Baranagar - Dakshineswar Metro
For Baranagar-Barrackpore & Dakshineswar and Noapara- Baranagar, the work was planned in 2 phases i.e. the first phase being Noapara-Baranagar-Dakshineswar and in the second phase, from Baranagar-Barrackpore. The first phase, i.e. from Noapara to Dakshineswar, the Metro corridor has been inaugurated and dedicated to the Nation by Hon'ble Prime Minister on 22.02.2021 for public use.
For the second phase of this Metro corridor, i.e. Baranagar-Barrackpore, a MoU was signed between State Government, Metro Railway and RVNL in October 2011. Original sanctioned alignment via B.T. Road was not agreed by State Govt. despite signing of the MoU in Oct' 2011 for closing of 2 pipelines and even after completion of new pipeline work of 64" dia by State Govt. Repeated observations raised by KMC have been complied by RVNL. However, Technical approval / NOC from State Govt. is still awaited. Pursuant to the Railway Board review on 24.05.2026, a joint meeting with KMC, RVNL, and DM/ Barasat was held on 25.05.2026. As per the Minutes of the meeting dated 25.05.2026, KMC proposed to sacrifice the existing 42-inch dia age old pipeline whereas RVNL requested to KMC for sacrificing the existing age old 48- inch dia pipeline with replacement of a new peoposed 72-inch dia MS pipeline from Tallah (TPS) to Palta (IGWTP) along with Metro construction work in parallel to maintain uninterrupted water supply to the City people and mitigate the future demand also. This will ease finalization of Metro alignment at earliest from Baranagar (Ex.) to Barrack pore as per the earlier submitted proposal to KMC. In the VC held on 26.05.2026 between Chairman & CEO/Railway Board and Chief Secretary/GoWB, RVNL was advised to examine laying a new 72-inch dia. pipeline, while KMC was directed to engage I IT KGP to assess adequacy of water supply under the proposed arrangement.
3.9.4.7 Phase Commissioning of Metro Project:
(i) Noarpara - Baranagar - Dakshineswar: The project has been inaugurated by Hon'ble PM on 22.02.2021 and Commercial Operation of train service started w.e.f. 23.02.2021.
(ii) Joka-Taratala in Joka - Esplanade Metro Corridor: 9.0 km of continuous stretch from Joka Depot has been completed. Major structures and stations have been completed at Joka, Thakurpukur, Shaker Bazar, Behala Chowrasta, Behala Bazaar, Taratala. The first phase i.e. Joka to Taratala of Joka-Esplanade Section has been inaugurated by Hon'ble Prime Minister on 30.12.2022 and commissioned on the same day.
(iii) Taratala-Majerhat Joka - Esplanade Metro Corridor: 2nd phase of 1.25 Km has been inaugurated by Hon'ble PM on 06.03.2024 and Commercial Operation of train service started w.e.f. 15.03.2024.
(iv) New Garia-Hemanta Mukhopadhyay in New Garia- Airport corridor: 5.4 Km has been inaugurated
by Hon'ble PM on 06.03.2024 and Commercial Operation of train service started w.e.f. 15.03.2024.
(v) Hemanta Mukhopadhyay to Beleghata in New Garia- Airport corridor: 4.4 Km commercial run has been started from 25.08.2025 after being dedicated to the nation by the Hon'ble Prime Minister on 22.08.2025.
3.10 Accidents
During 2025-26, no accident was reported from any of the project sites of RVNL.
3.11 ADB funded projects:
The first ADB loan (IND-1981) sanctioned for "Railway Sector Improvement" was closed on 31.12.2011. A 2nd ADB Loan has been sanctioned for funding of 5 projects, namely:
• Raipur-Titlagarh doubling
• Sambalpur-Titlagarh doubling
• Hospet-Tinaighat doubling
• Daund-Gulbarga doubling
• Pune-Guntakal Railway Electrification
The funding by ADB requires compliance of various loan covenants on resettlement and rehabilitation of project affected persons, procurement of works and stores following international competitive bidding and implementation of plans for mitigation of social and environmental impact norms. A Multi Tranche Financing Facility of $ 500 million has been agreed to by ADB. The loan agreement for first Tranche (Loan No. 2793-IND) of this MFF for an amount of $ 150 million was signed in July 2012 and the loan agreement for second Tranche (Loan No. 3108-IND) of this MFF for an amount of $ 130 million was signed in February 2014, the loan was closed on 20.12.2019 Project Agreement & Loan Agreement against ADB loan No. 3623-IND (Railway Sector Investment Program- Tranche III) for an amount of $ 130 million have been signed on 16.3.2018 and made effective on 07.06.2018. The loan was fully disbursed on 29 October 2021 and the loan account was closed effective on 2 December 2021. Project Completion Report (PCR) submitted to ADB and loan is fully closed.
Currently, the following five railway projects are funded through the Asian Development Bank (ADB) loan:
• Raipur-Titlagarh Doubling
• Sambalpur-Titlagarh Doubling
• Hospet-Tinaighat Doubling
• Daund-Gulbarga Doubling
• Pune-Guntakal Railway Electrification
The ADB funding requires compliance with respect to following parameters:
• Resettlement & rehabilitation of affected people
• International competitive bidding for procurement
• Environmental and social safeguard plans during implementation
The ADB loan supported railway capacity expansion and electrification projects in India, are tied to strict safeguards on social justice, environmental protection, and transparent procurement practices.
3.12Contracting:
As the size of projects being executed by RVNL is quite large, to ensure fast award and execution of projects, RVNL invites tenders consisting of multiple packages. Each tender may consist of up to 3 contract packages. This approach has a number of advantages such as:
a) Multiple contracts can be awarded through one tender which saves time and effort in invitation and finalization of tenders.
b) Both small and large agencies can compete for any contract package which increases competition.
c) Large agencies who are capable of executing big contracts can quote for multiple packages to achieve economy of scale and pass on the benefit to RVNL by quoting discounts in case of award of more than one package.
d) Smaller agencies, which would not be eligible to quote if the tender for the project was floated in a single package, are now able to compete in any of the contract packages individually as they may meet the qualification requirements of individual packages which are of comparatively smaller value.
During 2025-26, contracts worth approximately D4339.55 Cr. were awarded.
The following major contracts were awarded by the Company during the year:
• PACKAGE - 1C : Construction of Roadbed, Minor Bridges, Buildings, Installation of Track (excluding Supply of Rails, Sleeper & Thick Web Switches), and other Civil Engineering and General Electrical works in connection with New BG Railway Line between Pipaliya Nankar (excl.) - Budni (incl.) Stations (chainages 129.000 - 198.000 km) in Indore-Budni section of Bhopal Division West Central Railway in Madhya Pradesh State, India (D755.79crore)
• “Package-1B : Construction of Roadbed, Minor Bridges, Buildings, Installation of Track (Excluding Supply of Rails, Sleeper & Thick Web Switches), and other Civil Engineering and General Electrical Works in Connection With New BG Railway Line Between Kheri (Excl) - PipaliyaNankar Station (Chainages 57.400 - 129.000 Km) in Indore-Budni Section of
Bhopal Division West Central Railway In Madhya Pradesh State, India" (D699.98 Crore)
• "Construction of Foundations, Substructure & Superstructure along With River Training/Protection Work, Temporary & Allied works for 2 Important / Major Bridges in between Chainage Km 36+100 To Km 40+480, in connection with Bhanupali- Bilaspur-Beri New Railway Line in District Bilaspur of Himachal Pradesh State, India" (D 401.98 Crore)
• Supply, Erection, Testing & Commissioning Of Electro Mechanical (E&M comprising of 33/11kv & 11/0.433kv GIS Substations, HT & LT Cables, Lighting, Ups System, Ventilation Systems & Fire Fighting Systems and associated works for Tunnel T-1, T-2, T-3 & T-4 under package E-1 Of Rishikesh- Karanprayag New BG Rail Line Project In The State Of Uttarakhand. (D388.39 Crore)
• "Construction of Foundations, Substructure & Superstructure along With River Training/Protection Work, Earthwork & allied works for Rail Bridge 16A (CH. 0+901.158 to 1+066.525), Rail Bridge 16B (CH.0+888.967 TO 1+054.711) and Road Bridge 2 (CH. 0+050 TO 0+167.995) at Karanprayag Yard in connection with New Single Line Broad Gauge Rail Link Between Rishikesh and Karanprayag (125km) in State of Uttarakhand, India" (D283.59crore)
• Design, Supply, Erection & Testing and commissioning of Electrical and Mechanical works of 4 stations including tunnels in Mominpur- Esplanade underground section in Joka-Esplanade Corridor of Metro Railway, Kolkata, (West Bengal), India (D229.80crore)
• Package 4 : Construction of Station Buildings, Platforms, FOBS, Circulating area amenities and other Misc. Yard Structures along with General Electrical works in Karanprayag Yard (km - 124+990) in connection with Rishikesh - Karanprayag 125km long New BG Rail Line Project in the State of Uttarakhand, India. (D 224.10CRORE)
• Construction of Viaduct of length 2.405km (ch:- 2.705 to 5.110) for Electrified New BG Railway Line between Mangaliyagaon and Panod Stations in Bhopal Division of West Central Railway In Madhya Pradesh State, INDIA. (D 161.17CRORE)
• PACKAGE 2 : Construction of Station Buildings, Platforms, FOBS, Circulating area amenities and other Misc. Yard Structures along with General Electrical Works in Devprayag (km - 47+390), Janasu(km - 62+220), Maletha (km - 66+970) and Srinagar (km-72+148) Yards in connection with Rishikesh - Karanprayag 125km long New BG Rail Line Project in the state of Uttarakhand, India (D 144.95CRORE)
• "Special Limited Tender for "Construction of Reinforced Soil Wall from (Ch. 124+460 to 124+900) and Formation Works Ch. 125+180 to 125+887) along with slope stabilization in connection with New Single Line Broad Gauge Rail Link between Rishikesh and Karanprayag (125km) in the State of Uttarakhand, India" (D128.17crore)
• Package 3 : Construction sf Station Buildings, Platforms, FOBs, Circulating area amenities and other misc. yard structures along with general electrical works in Dhari Devi (Km-83+389), Tilani (Km-101 +004),Gholtir (Km 108+554.991) and Gauchar (Km-116+393.588) yards in connection with Rishikesh - Karnprayag 125km Long New BG Rail Line Project in the State of Uttarakhand, India. (D106.61crore)
• "Package-VI - Installation and linking of BG railway track, P-way material supply, Track Ballast supply, Mobile Flash Butt Welding of Joint and all other associated P-way work (excluding supply of rails, line/ordinary wider base PSC sleepers) in section between Yavatmal (Ex.) to Belgaon (Ex.) from Km 78 to Km 157 in connection with Yavatmal-Nanded New BG line of Central Railway in Maharashtra State, India" (D100.64crore)
• Design, Engineering, Supply, Erection, Testing & Commissioning of Electro Mechanical (E&M) System which includes 33/11kV Substations & 11/0.433kV Substations, 33kV & 11kV Power Cable Network, DG Sets, Ventilation & Control System, lighting, UPS system, Fire Fighting system & SCADA System, etc. and associated works complete in all respect as required for tunnel T-1 to T-7 between Ch. 0.000 to Ch. 20.000 in connection of Bhanupli-Bilaspur-Beri New Railway Line Broad Gauge Rail Link in Districts Rupnagar of Punjab and Bilaspur of Himachal Pradesh States, India". (D86.38crore)
• Design, Supply, Erection, Testing & Commissioning of Traction Sub Stations with associated Switching Posts for 2 x 25 KV AT feeding system in Phaphamau- Janghai sections (incl. Phaphamau-Prayagraj section) of Lucknow Division of Northern Railway in connection with doubling of tracks between Phaphamau(Excl.)Janghai(Excl.) Section of Lucknow Division on N. Railway in the state of Uttar Pradesh, India on EPC mode (D65.67crore)
• 'PACKAGE - EHT -3: Design, Supply, Erection, Testing and Commissioning of 132KV /220KV transmission line owned by Madhya Pradesh power transmission company limited as diversion / modification work (including identification & resolution of row issues by payment of compensation to the affecting land owners) due to infringement in the alignment of proposed new B.G. Railway line between mangaliyagaon (Indore) - Budni section on Ratlam division of western railway and Bhopal division of West Central Railway in the State of Madhya Pradesh, India' (D59.88crore)
• Extension of Beleghata and Barun Sengupta Metro Stations above platform level in New Garia-Airport metro corridor of Kolkata Metro Railway, West Bengal, India. (D55.40crore)
• Construction Of Station Buildings, Platforms, Fobs, Circulating area amenities and other misc. yard structures along with general electrical works in Shivpuri (Km - 18+095) and Byasi (Km-32+395) Yards in connection with Rishikesh - Karnprayag 125 km Long New BG Rail Line Project in the State of Uttarakhand, India). (D51.67crore)
• Package-3: Design, Supply, Erection, Testing and Commissioning of 220KV, 3Phase D/C transmission line (12KM) from Kumhari (PGCIL GSS) to Bhilai TSS, Bhilai TSS to Rajnandgaon TSS (55 KM), Rajnandgaon TSS to Paniajob TSS (45KM), Bhilai TSS to Urkura Bus Coupler (35 KM) and Urkura Bus Coupler to Urkura TSS (5 KM); Extension of 220KV bay at Kumhari (PGCIL); LILO 2 Nos at Bhilai&Rajnandgaon and Bus Coupler 1 No at Urkura along with associated works in connection with Direct Power Supply from Central Generating Agencies over South East Central Railway, Bilaspur, Chhattisgarh (India). (D49.95crore)
• "Design, Supply, Installation, Testing & Commissioning of Integrated Communication System for Tunnels (T1-T7) consisting of VHF communication, CCTV, PA System, Emergency Call and Service Telephone & IPIS at stations in connection with New Single Broad-Gauge Rail Line Between the Bhanupali-Bilaspur-Beri Section in the state of Punjab and Himachal Pradesh, India". (D47.25 Crore)
• Package - EHT - 1: Design, Supply, Erection, Testing and Commissioning of 400KV transmission line owned by Power Grid Corporation of India limited as diversion / modification work (including setup of emergency restoration system (ERS) with identification & resolution of row issues by payment of compensation to the affecting land owners) due to infringement in the alignment of proposed New B.G. Railway line between Mangaliyagaon (Indore) - Budni section on Ratlam division of Western Railway and Bhopal division of West Central Railway in the state of Madhya Pradesh, India. (D46.11 Crore)
• 'Package - EHT -3: Design, Supply, Erection, Testing and Commissioning of 132KV /220KV Transmission line owned by Madhya Pradesh Power Transmission company limited as diversion / Modification work (including identification & resolution of row issues by payment of compensation to the affecting land
owners) due to infringement in the alignment of proposed New B.G. railway line between Mangaliyagaon (Indore) - Budni section on Ratlam division of western railway and Bhopal division of West Central Railway in the state of Madhya Pradesh, India' (D32.95 Crore)
• Design, Supply, Erection, Testing & Commissioning of 2X25 KV, 50 Hz, Single Phase, Traction Over¬ Head Equipment, Switching Station, SCADA, General Electrical Services Works along with Telecommunication work, Civil Engineering work and other associated works between section Taroki (Excl.) - Rowghat (Incl.) 18.85 RKM / 24.74 TKM of Raipur Division in South East Central Railway, Chhattisgarh, INDIA. (D32.44crore)
• 'Package - EHT - 4: Design, Supply, Erection, Testing and Commissioning of 132KV / 220KV Transmission Line owned by Madhya Pradesh Power Transmission Company Limited as Diversion /Modification Work (Including Identification & Resolution Of Row Issues by payment of Compensation To The Effecting Land Owners) due to infringement in the alignment of proposed New B.G. Railway Line between Mangaliyagaon (Indore) - Budni Section on Ratlam Division of Western Railway and Bhopal Division of West Central Railway in the State of Madhya Pradesh, India’(D25.08crore)
• 'Conversion of 33kV / 11kV Overhead Power Lines / Distribution Lines into Underground Cable Lines including Replacement / Relocation of associated lines & Distribution Transformers with H-Beam, PCC Poles structure / lines to remove infringement of Alignment of New Electrified Broad Gauge Railway Line between Kheri (57.400 KM) to Pipaliya Nanker (129.00 KM) Section in Bhopal Division of West Central Railway in the State of Madhya Pradesh, India' (D21.86 Crore)
• Execution of P.Way track linking, precast bridge with launching, fixing of RH Girder and miscellaneous building works for doubling of Cansaulim - Vasco section of Hospet-Vasco doubling project in the State of Goa" . (D 19.43 Crore)
• Krishna Canal junction Yard remodellig - Balance works at KCC yard including formation works, upgrading of Platform No.8 & 9, extension of minor bridges, track linking, assembling & laying of P&C, Dismantling of P&C, Modification of FOB, Slewing of track, linking of track in connection with Construction of 3rd Line between KCC-KRV Section in Vijaywada Division of South Central Railway, india" (D 15.44 Crore)
• General Electrical, Power Distribution, Lift, Fire detection & Alarm and Fire Fighting works for 240
nos. Dwelling Units (DUs) at Panagarh Military Station, West Bengal, India" (D11.30 Crore)
• 'Improvement of long haul siding and construction of goods loading platform at Sundlak station in connection with Bina - Kota doubling project in Kota Division of West Central Railway. (D9.91 crore)
• Design, Supply, Erection, Testing & Commissioning of Feeder wire, AEC, BEC, Super Mast, Auto Transformer and other modificaiton work for 2x25KV traction system between section Dallirajhara (Excl.) - Bhanupratappur SP (Excl.) 27.850 RKM/30.850 TKM of Raipur Division in South East Central Railway, Chhattisgarh, India (D7.86crore)
• Construction of HL Platform, Surfacing, Fixing of chequered tiles at Island platform No. 2 & 3 of KVQ, 4 & 5 of MDJ and 1,2,3 & 4 of SQS Station and other Miscellaneous Works in connection with construction of 3rd Line from Sonnagar to Garhwa Road in DDU Division of East Central Railway (D7.66crore)
• 'Construction of 6 m wide Foot Over Bridge and other miscellaneous work at Japla (JPL) yard in connection with construction of 3rd line from Sonnagar to Garhwa Road in DDU Division of East Central Railway' (D7.11crore)
• Construction of W/R wall, U- through wall of 5 nos. bridges, Approach road of 2 RUBs and Approach road of 3 Halts and other misc. work from Gonpura to Jatdumri section in connection with construction of new line from Neora (including) to Jatdumri (excluding) (18.40 Km) on Danapur Division of East Central Railway in Bihar, India (D7.06 Crore)
• Construction of G+4 Residential Building, G+1 Store Building, 2 nos. Container for Storage and other allied works in connection with shifting of 42 nos. Dhobi line hutments inside premises of Kolkata Armed Police HQ, Kolkata in connection with construction of Mominpur - Esplanade underground section of Joka - Esplanade Metro Railway Corridor. (D6.86 Crore)
• Construction of RVNL office building at Saket Nagar, Bhopal on Railway land’ (D6.48 Crore)
• Construction of G+2 Building and other allied works inside premises of Consulate General of Nepal at National Library Avenue, Kolkata in connection with Construction of Mominpur-Esplanade underground Section of Joka-Esplanade Metro Railway Corridor" (D6.25 Crore)
• Execution for Laying of 1100 mm and 16mm wall thick MS pipe by Trenchless Method and Pushing the Pipe by Hydraulic Jack in the side drain between Duburi - Baguapal Block Section in connection with
Angul-Sukinda Railway Line under Khurda Road Division of East Coast Railway (D6.21 Crore)
• Construction of Goods platform (With released PSC Sleepers), linking of track for line no.7 at Japla and other miscellaneous work at Japla (JPL) in connection with construction of 3rd line from Sonnagar to Garhwa Road in DDU Division of East Central Railway (D5.72 crore)
• 'Modification of existing 132KV Vontithadi-Garividi S/C line to improve the ground clearance for 3rd line constructed in between Gotlam-Vizianagaram Railway crossing (Loc.No:113-114) at railway Loc.No. 463/12 near KL Puram (V), Vizianagaram District in connection with 3rd line project between Titlagarh- Vizianagaram in WAT division of East coast Railway, India (D5.64 crore)
• Repair and Mainenance contract of Railway Officers Encalve, Moti Bagh, New Delhi (D5.48 crore)
• Construction of U-trough wall (LHS & RHS) of RUB, Br.No.26 (Ch.11+650) in connection with Neora- Jatdumri New bg Line Project (D5.30 crore)
• Package- AAI Subway: "Construction of AAI Subway/ Underpass across VIP Road from Airport Operational Area to AAI Residential Colony at NSCBI Airport, Kolkata passing below the Metro Ramp structure of New Garia-Airport Metro Corridor, West Bengal. (D5.12 crore)
• Execution of General Electrical works for the section Gotlam(Excl.)-Vizinagaram(Excl.) including Bye- pass line between stations Gotlam-Nellimarla and associated temporary diversion of power lines in connection with Vizianagram - Titlagarh 3rd line works between TIG-VZM in WAT division of East Coast Railway, India. (D3.40 crore)
• Augmentation of existing 11/0.433 KV Sub¬ Station including Supply, Installation, testing & commissioning of 02 nos.1MVA power transformers, LT & HT panels, laying of HT & LT cables and other
associated works including heavy repair of existing substation building at DRM office Moradabad in connection with New MTCC Building at Moradabad for 125kM New BG Rail Line between Rishikesh and Karnprayag in the State of Uttarakhand. (D3.18 crore)
• Provision of Barricading as Protection Measure in deep cutting Area of Angul - Sukinda New Line near Duburiunder Khurda road division of East coast Railway in State of Odisha, India" (D1.39 crore)
Besides these Works Contract, FLS, DD&PMC and PMC contracts on nomination basis for D41.89 crore have also been awarded during 2025-26.
4. PROJECT PLANNING & DEVELOPMENT 4.1 PUBLIC PRIVATE PARTNERSHIP (PPP) in Indian Railway Connectivity Projects Strategic Overview: -
As part of Rail Vikas Nigam Limited's (RVNL) mandate to undertake project development, mobilize financial resources, and implement projects aimed at strengthening the Golden Quadrilateral network and enhancing connectivity to various ports, five Special Purpose Vehicles (SPVs) have been incorporated as Joint Venture (JV) companies on Public Private Partnership (PPP) models. RVNL holds a minimum equity participation of 26% in each of these SPVs, demonstrating its strategic commitment in the development and implementation of these critical rail infrastructure projects.
Key Achievements: -
Through these SPVs, RVNL has successfully mobilized a cumulative investment of C10,839.47 crore, comprising C3,959.91 crore through equity and C6,879.56 crore through debt financing. Out of the total investment mobilized, RVNL has contributed C1,544.65 crore towards equity in these five SPVs, which constitutes only about 14.25% of the aggregate project investment, thereby demonstrating significant leveraging of resources through the SPV model (refer table below).
|
SPV
|
Length
(Km)
|
Paid-up
Equity
|
RVNL
Equity
|
Debt
|
Total
Investment
|
|
Kutch Railway Company Ltd.
|
301
|
821.00
|
410.50
|
1,584.41
|
2,405.41
|
|
Bharuch Dahej Railway Company Ltd.
|
67.12
|
155.11
|
55.00
|
230.00
|
385.11
|
|
Krishnapatnam Railway Company Ltd.
|
113
|
625.00
|
311.00
|
1,074.97
|
1,699.97
|
|
Haridaspur Paradip Railway Company Ltd.
|
82
|
1,300.00
|
390.00
|
1,451.61
|
2,751.61
|
|
Angul Sukinda Railway Ltd.
|
104
|
1,058.80
|
378.15
|
2,538.57
|
3,597.37
|
|
Total
|
667.12
|
3,959.91
|
1,544.65
|
6,879.56
|
10,839.47
|
(a) Kutch Railway Company Limited (KRC) Salient Features of the Project: - a) Kutch Railway Company Limited (KRC)
|
Railway/Division/State
|
Western Railway / Ahmedabad / Gujarat
|
|
|
Project Type& Length
|
Gauge Conversion, 301 Km
|
|
|
Year of Sanction
|
1988-89
|
|
|
Date of Transfer to RVNL
|
14.05.2003
|
|
|
Date of MoU
|
03.01.2004
|
|
|
Date of EOI
|
NA
|
|
|
Date of Incorporation
|
22.01.2004
|
|
|
Shareholders Agreement signed on
|
22.04.2004
|
|
|
Traffic Guarantee Agreement signed on
|
Not signed
|
|
|
Concession Agreement signed on
|
08.11.2005
|
|
|
Construction Agreement signed on
|
GC - 06.10.2005, DL-13.08.2018, RE - 09.02.2021
|
|
|
O&M Agreement signed on
|
21.08.2005
|
|
|
Original cost (DCrore)
|
344.63
|
|
|
Project cost (D Crore)
|
550.00
|
|
|
Equity Participants
|
Rail Vikas Nigam Limited 410.50
|
50.00%
|
| |
Deendayal Port Authority 213.46
|
26.00%
|
| |
Adani Ports & SEZ Limited 164.20
|
20.00%
|
| |
Govt. of Gujarat 32.84
|
4.00%
|
| |
Total (D Crore) 821.00
Note: -
|
100.0%
|
| |
• Bonus shares amounting to C50 crore issued ir ratio of 1:4.
|
i November 2011 in the
|
| |
• Doubling and Railway Electrification works
|
executed at a cost of
|
| |
C3,153.70 crore and C755 crore respectively. Full project commissioned on 24.02.2023 and RE completed on 24.03.2023.
|
|
Commercial Operations Date (COD)
|
01.07.2006
|
|
|
tailway/Division/State Western Railway/Vadodara/Gujarat
|
|
Jroject Type& Length Gauge Conversion, 67.12 Km
|
|
ear of Sanction
|
2005-06
|
|
|
|
Date of Transfer to RVNL
|
22.03.2006
|
|
|
|
Date of MoU
|
13.01.2005
|
|
|
|
Date of EOI
|
27.02.2006
|
|
|
|
Date of Incorporation
|
15.11.2006
|
|
|
|
hareholders Agreement signed on
|
12.01.2007
|
|
|
|
rraffic Guarantee Agreement signed on
|
Not signed
|
|
|
|
oncession Agreement signed on
|
25.06.2008
|
|
|
|
onstruction Agreement signed on
|
01.07.2009
|
|
|
|
&M Agreement signed on
|
Not signed
|
|
|
|
Driginal cost (D Crore)
|
262.00
|
|
|
|
Jroject cost (D Crore)
|
395.00
|
|
|
|
Equity Participants
|
Rail Vikas Nigam Limited
|
55.00
|
35.46%
|
| |
Gujarat Maritime Board
|
17.86
|
11.51%
|
| |
Gujarat Industrial Development Corporation
|
17.86
|
11.51%
|
| |
Adani Petronet (Dahej) Port Private Limited
|
17.33
|
11.17%
|
| |
Gujarat Narmada Valley Fertilizer Company
|
13.53
|
8.72%
|
| |
Hindalco Industries Limited
|
13.53
|
8.72%
|
| |
Dahej SEZ Limited Texmaco West Rail Limited
|
10.00
|
6.45%
|
| |
(Formerly known as Jindal Rail Infrastructure Limited)
|
10.00
|
6.45%
|
| |
Total (D Crore)
|
155.11
|
100.0%
|
|
ommercial Operations Date (COD)
|
08.03.2012
|
|
|
|
Railway/Division/State
|
South Central Railway/Vijayawada/Andhra Pradesh
|
|
|
Project Type& Length
|
New Line, 113.12 Km
|
|
|
Year of Sanction
|
2006-07
|
|
|
Date of Transfer to RVNL
|
14.05.2003
|
|
|
Date of MoU
|
22.11.2005
|
|
|
Date of EOI
|
27.02.2006
|
|
|
Date of Incorporation
|
11.10.2006
|
|
|
Shareholders Agreement signed on
|
13.10.2006
|
|
|
Participation Agreement- I signed on
|
23.02.2008
|
|
|
Participation Agreement -II signed on
|
12.10.2020
|
|
|
Traffic Guarantee Agreement signed on
|
Not signed
|
|
|
Concession Agreement signed on
|
23.11.2007
|
|
|
Construction Agreement signed on
|
29.09.2011
|
|
|
O&M Agreement signed on
|
06.01.2012
|
|
|
Revised O&M Agreement signed on
|
08.11.2021
|
|
|
Original cost (D Crore)
|
732.81
|
|
|
Estimated Project cost (D Crore)
|
2831.00
|
|
|
Equity Participants
|
Rail Vikas Nigam Limited 311.00
|
49.76%
|
| |
Sagarmala Development Co. Ltd 125.00
|
20.00%
|
| |
Adani Krishnapatnam Port Co Ltd 81.00
|
12.96%
|
| |
National Mineral Development Corporation Ltd 40.00
|
6.40%
|
| |
Govt. of Andhra Pradesh 35.00
|
5.60%
|
| |
Bramhani Industries Ltd 33.00
|
5.28%
|
| |
Total (D Crore) 625.00
|
100.0%
|
|
Commercial Operations Date (COD)
|
a. Venkatachalem - Nidiguntapalem - 01.10.2008
b. Nidiguntapalem - Krishnapatnam - 28.02.2009
c. Doubling of 21 km line from VKT to KAPT - 02.03.2014
d. The complete connectivity was commissioned in June 2019
|
|
d) Haridaspur Paradip Railway Company Limited (HPRCL) Salient Features of the Project:
|
Railway/Division/State
|
East Coast Railway/Khurda Road/Odisha
|
|
|
|
Project Type & Length
|
New Line, 82 Km
|
|
|
|
Year of Sanction
|
1996-97
|
|
|
|
Date of Transfer to RVNL
|
14.05.2003
|
|
|
|
Date of MoU
|
24.02.2005
|
|
|
|
Date of EOI
|
21.01.2006
|
|
|
|
Date of Incorporation
|
25.09.2006
|
|
|
|
Shareholders Agreement signed on
|
11.10.2006
|
|
|
|
Traffic Guarantee Agreement signed on
|
04.04.2008
|
|
|
|
Concession Agreement signed on
|
20.12.2007
|
|
|
|
Construction Agreement signed on
|
11.08.2009
|
|
|
|
O&M Agreement signed on
|
24.10.2021
|
|
|
|
Original cost (D Crore)
|
301.64
|
|
|
|
Estimated Project cost (D Crore)
|
2397.00
|
|
|
|
Equity Participants
|
Rail Vikas Nigam Limited
|
390.00
|
30.00%
|
| |
Sagarmala Development Company Ltd.
|
336.79
|
25.91%
|
| |
Govt. of Odisha
|
237.79
|
18.29%
|
| |
Paradip Port Trust
|
138.52
|
10.66%
|
| |
Orissa Mining Corporation
|
110.00
|
8.46%
|
| |
Essel Mining & Industries Ltd
|
30.00
|
2.31%
|
| |
Rungta Mines Ltd
|
30.00
|
2.31%
|
| |
MSPL Ltd
|
15.00
|
1.15%
|
| |
Jindal Steel Power Limited
|
5.00
|
0.38%
|
| |
Steel Authority of India Ltd.
|
5.00
|
0.38%
|
| |
Odisha Industrial Infrastructure Development Corporation (IDCO)
|
1.90
|
0.15%
|
| |
Total (D Crore)
|
1300.0
|
100.0%
|
|
Commercial Operations Date (COD)
|
30.07.2020
|
|
|
|
Railway/Division/State
|
East Coast Railway/Khurda Road/Odisha
|
|
|
|
Project Type & Length
|
New Line with Y-connection, 104.242 Km
|
|
|
|
Year of Sanction
|
1997-98
|
|
|
|
Date of Transfer to RVNL
|
22.02.2006
|
|
|
|
Date of MoU
|
19.11.2008
|
|
|
|
Date of EOI
|
17.06.2008
|
|
|
|
Date of Incorporation
|
20.02.2009
|
|
|
|
Shareholders Agreement signed on
|
27.05.2009
|
|
|
|
Traffic Guarantee Agreement signed on
|
Not signed
|
|
|
|
Concession Agreement signed on
|
14.05.2010
|
|
|
|
Construction Agreement signed on
|
24.04.2015
|
|
|
|
O&M Agreement signed on
|
Not signed
|
|
|
|
Original cost (D Crore)
|
391.00
|
|
|
|
Estimated Project cost (D Crore)
|
2913.00
|
|
|
|
Equity Participants
|
Rail Vikas Nigam Limited
|
378.15
|
35.71%
|
| |
Govt. of Odisha
|
259.47
|
24.51%
|
| |
CONCOR
|
250.80
|
23.69%
|
| |
Odisha Mining Corporation
|
106.18
|
10.03%
|
| |
Jindal Steel Power Limited
|
60.00
|
5.67%
|
| |
Odisha Industrial Infrastructure Development Corporation (IDCO)
|
4.20
|
0.40%
|
| |
Total (D Crore)
|
1058.80
|
100%
|
|
Commercial Operations Date (COD)
|
01.03.2023
|
|
|
4.2 Details of SPV's/JV's of Rail Vikas Nigam limited (RVNL) for other projects
Rail Vikas Nigam Limited has following JVs/SPVs for other projects:
|
Details of Equity of RVNL's new SPVs/JVs (as on 31.03.2026)
|
|
S.
|
Name of SPV
|
Date of
|
Paid up Equity
|
RVNL's Equity
|
Partners' Equity
|
|
No.
|
Incorporation
|
Crore
|
Crore
|
%age
|
Crore
|
%age
|
| |
|
(D)
|
(D)
|
(D)
|
|
1.
|
Shimla Bypass Kaithlighat Shakral Pvt. Ltd.
|
05.08.2022
|
130.10
|
65.05
|
50.00%
|
65.05
|
50.00%
|
|
2.
|
Chatra Expressways Pvt. Ltd.
|
24.04.2023
|
3.01
|
1.47
|
49%
|
1.54
|
51%
|
|
3.
|
Kinet Railway Solutions Limited
|
19.04.2023
|
411.00
|
102.75
|
25%
|
308.25
|
75%
|
|
4.
|
JGPL-RVNL EPC Private Limited
|
15.01.2024
|
0.01
|
0.0049
|
49%
|
0.0051
|
51%
|
# Other Investments (upto 10%): Chennai MMLP, Indore MMLP, Bengaluru MMLP and IPRCL.
a) Shimla Bypass Kaithlighat Shakral Pvt. Ltd. (SBKSPL)
The Government of India had entrusted to the Authority (NHAI) the development, maintenance and management of Greenfield alignment of National Highway No 5-including the section from km 128.835 to km 146.300 (approx. 17.465 km). The Authority had resolved to Construction of 4 Laning of NH-5 from Kaithlighat to Shakral Village for Design Length 17.465km in the State of Himachal Pradesh by Four-Laning thereof on design, build, operate and transfer (the "DBOT Annuity" or "Hybrid Annuity") basis, which shall be partly financed by the Concessionaire who shall recover its investment and costs through payments to be made by the Authority.
The Consortium has been promoted and incorporated the Concessionaire as a limited liability company under the Companies Act 2013 named Shimla Bypass Kaithlighat Shakral Pvt. Ltd. by Rail Vikas Nigam Ltd. and M/s S P Singla Constructions Pvt. Ltd as its lead members for the execution of the project.
Brief of the Project:
|
Location and State
|
4-Lane Bypass, Package-I, Kaithlighat to Shakral, Shimla, Himachal Pradesh
|
|
Project Type & Length
|
Hybrid Annuity Mode & 17.465 km
|
|
|
|
Date of MoU
|
15.05.2022
|
|
|
|
Date of Incorporation
|
05.08.2022
|
|
|
|
Project cost
|
• id Project Cost (BPC) - C1844.77 Crore excluding GST
• First Year O&M Bid - C2.77 Crore excluding GST
|
|
|
| |
Adjusted Bid Price - C 1637.96 Crore (NPV of BPC and First Year O&M)
|
|
|
Equity Participants and their % share
|
|
|
|
|
S. Representative of Nominees' Name
No. company
|
No. of Shares
|
% of
Shareholding
|
| |
1. M/s S P S Construction Mr. Sat Paul Singla India Private Limited
(Formerly known as Mr. Deepak Singla SP Singla Construction India Private Limited)
|
6,50,50,000
|
50
|
| |
2. M/s Rail Vikas Nigam Mr. Chandan Limited (RVNL)- Kumar Verma
|
6,50,50,000
|
50
|
| |
Mr. Rakesh Sabharwal
|
|
|
| |
|
|
|
|
Anticipated Commercial Operations Date (COD)
|
After the end of Construction period tentatively 20.04.2026
|
|
b) Chatra Expressways Pvt. Ltd.
Chatra Expressways Private Limited (CEPL) is a Special Purpose Vehicle (SPV) formed as a joint venture between Rail Vikas Nigam Limited (RVNL) and its project partner for the development of a national highway project under the Bharatmala Pariyojana on the Hybrid Annuity Mode (HAM). The company has been established to undertake the construction, operation and maintenance of the project in accordance with the concession agreement executed with the National Highways Authority of India (NHAI). CEPL reflects RVNL's strategic expansion into the highway infrastructure sector and reinforces the Company's commitment to developing multi-modal infrastructure through efficient project execution and long-term asset management.
|
Location and State
|
Chandauli, Uttar Pradesh to Bangam, Kolkata
|
|
Project Type & Length
|
Construction of 6-lane Greenfield Varanasi-Ranchi-Kolkata Highway from Sonepurbigha village to junction with NH-22 (Chatra Bypass) near Chatra from km 184.700 to km 222.000 under Bharatmala Pariyojana in the State of Jharkhand on Hybrid Annuity Mode (Package 8).
The length of the project is 37.300 Kms.
|
|
Date of MoU
|
01.03.2023
|
|
Date of Incorporation
|
24.04.2023
|
|
Project cost
|
C 1271.99 Crores (Without GST)
|
|
Equity Participants and their
|
Tracks & Towers Infratech (P) Ltd.- 51%
|
|
% share
|
Rail Vikas Nigam Limited- 49%
|
|
Construction Period
|
730 days (24 months)
|
|
Scheduled Completion
|
730 Days from Appointed Date (Additional 90 Days)
|
c) Kinet Railway Solutions Ltd.
RVNL, in collaboration with its consortium partners, has signed the prestigious Manufacturing cum Maintenance Agreement of Vande Bharat Trainsets including upgradation of the Government Manufacturing Units & Trainset Depots. This project is being executed through a Special Purpose Vehicle (SPV) named Kinet Railway Solutions Limited (KRSL), jointly owned by RVNL and its consortium partners namely JCS Meterowagonmash (MWM), JSC Locomotive Electronic Systems (LES), and Rail Vikas Nigam Limited (RVNL). The shareholding of the KRSL as on Marrch 31,2026 is as follows due to changes in shareholding pattern of the company on the approval of Indian Railway:
Acting as the Technology Partner, KRSL is spear heading
the implementation of this visionary initiative.
Key highlights of this project include:
• KRSL has been entrusted with the manufacturing of 120 Vande Bharat Trainsets at the Manufacturing Unit located in Latur, Maharashtra.
• A planned maintenance regime has been devised, earmarking three designated depots - Bijwasan, Jodhpur, and Thanisandra - for the servicing and upkeep of these cutting-edge trainsets, ensuring their operational excellence for a period spanning 35 years.
• Comprehensive infrastructural planning, including the provision of state-of-the-art facilities as well as machinery, has been undertaken to equip the
designated depots, ensuring seamless operations and maintenance activities.
• The project timeline entails the delivery of the first prototype of the Vande Bharat Trainset to the Indian Railways by December 2026, followed by second prototype by February 2027. Regular deliveries follow marking a significant milestone in the nation's pursuit of advanced railway infrastructure.
• The Production was started at its Latur factory in February 2026.
• KRSL has received 2 internation design awards for its Vande Bharat Sleeper train design:
• The exterior design concept of the new Vande Bharat Sleeper Train, developed by KRSL, has been recognized as a winner of the Red Dot Award: Design Concept 2026 in the Trains, Planes and Watercraft category. This prestigious international award is one of the world's most influential honors in industrial and mobility design. The international jury praised the project for its vision of combining modern design language trends with cultural depth.
• The Vande Bharat Sleeper First AC compartment concept, developed by KRSL, has received the prestigious international 2026 A' Design Award for its outstanding contribution to mobility and transportation design. The international jury highly praised the project for its passenger-centric approach, thoughtful functionality, and refined visual identity, granting it the Bronze A' Design Award in the 2026 edition of the competition.
|
Location and State
|
New Delhi, India
|
|
Project Type
|
"Manufacturing cum Maintenance of Vande Bharat Trainsets including upgradation of the Government Manufacturing Units & Trainset Depots"
- 200 Vande Bharat Train sets of Sleeper version, each of 16 cars.
- Supply and undertake comprehensive maintenance thereof for a period of 35 years.
The L1 selected bidder would have to manufacture/assemble total 120 Trainsets at Railway's Marathwada Rail Coach Factory (MRCF)/Latur.
The L2 selected bidder would have to manufacture/assemble total 80 Trainsets at Railway's ICF/Chennai.
|
|
Date of MoU
|
14.11.2022
|
|
Date of Incorporation
|
19.04.2023
|
|
Project cost
|
The total quantity is 120 Trainsets and cost per set is C120 Crores. (as per LOA)
|
|
Equity Participants and their
|
RVNL- 25%
|
|
% share
|
Joint Stock Company Metrowagonmash- 35%
Joint Stock Company Locomotive Electronic Systems- 40%
|
The RVNL has following wholly owned Subsidiary Companies in India and abroad:
1. HSRC Infra Services Limited
2. Masakani Paradeep Road Vikas Limited
3. Sabbavaram Sheelanagar Road Development Limited
4. RVNL Infra South Africa
5. RVNL Infra Middle East (Oman)
6. RVNL Middle East Contracting L.L.C. (Dubai)
7. Rail Vikas Nigam LLC (Uzbekistan)
8. Rail Vikas Nigam Ltd. Company (One Person) (Kingdom of Saudi Arabia)
d) JGPL-RVNL EPC PRIVATE LIMITED
JGPL-RVNL EPC Private Limited is a joint venture company formed by Rail Vikas Nigam Limited (RVNL) and Jakson Green Private Limited to undertake engineering, procurement and construction (EPC) projects in the renewable energy sector. The company has been established to execute large-scale grid-connected solar power projects integrated with Battery Energy Storage Systems (BESS), supporting the transition towards sustainable and clean energy infrastructure. Through the combined expertise of RVNL in infrastructure development and Jakson Green in renewable energy solutions, the joint venture aims to deliver technologically advanced and reliable energy projects while contributing to India's and international clean energy initiatives.
|
Location and State
|
A 626, 6th Floor, DLF Tower A, Jasola, Sarita Vihar, South Delhi - 110076
|
|
Project Type
|
Grid Connected Solar PV Project along with Battery Energy Storage System (250 MW - Solar and 63 MW BESS)
|
|
Date of Incorporation
|
15.01.2024
|
|
Project cost
|
Approx. US$157.82 million (C 1,326 crore)
|
|
Equity Participants and their
|
RVNL- 49%
|
|
% share
|
Jakson Green Private Limited-51%
|
|
Anticipated Commercial Operations Date (COD)
|
16 September 2025 (scheduled commissioning)
|
5. PERSONNEL DEVELOPMENT
Human Resources continued to remain a key strategic enabler for Rail Vikas Nigam Limited (RVNL) in achieving its business objectives during the year. The Company's HR philosophy is centred on attracting, developing, motivating and retaining a highly competent workforce capable of delivering complex infrastructure projects across the country. RVNL has consistently maintained a lean yet professionally skilled workforce, supported by progressive HR policies and a performance-oriented work culture.
Considering the dynamic and project-based nature of its operations, RVNL adopts a balanced manpower strategy comprising experienced officers on deputation from Indian Railways and other Government organizations, alongside a steadily expanding regular cadre.
As on 31st March, 2026, the on-roll strength of the Company stood at 357 employees, comprising 250 regular employees and 108 officers on deputation.
RVNL continued to review and strengthen its employee- friendly policies aimed at improving employee engagement, productivity and organizational effectiveness. The Company provides a conducive work environment supported by competitive compensation, welfare measures, transparent career progression policies and performance-based recognition systems.
Learning and Development
Continuous learning and capability building remained an important focus area during the year. Employees at various levels were nominated for in-house, external and customized training programmes covering technical, managerial, financial, contractual, digital and behavioural competencies. The training initiatives were designed to enhance professional capabilities, leadership skills and adaptability to emerging technologies and evolving business requirements, thereby enabling employees to effectively contribute to the Company's expanding and diversified portfolio of infrastructure projects.
Employee Recognition
RVNL continued its tradition of recognizing and rewarding excellence through its Annual Day celebrations. Individual Awards, Group Awards, Shields and Cash Awards were presented to employees and project units demonstrating outstanding performance, innovation, commitment and excellence in project execution. Such recognition serves as an important motivational tool and reinforces the Company's culture of meritocracy and high performance.
Employee Welfare
Employee welfare continued to receive high priority during the year. In line with the Government guidelines and the Company's commitment towards employee well¬ being, various welfare initiatives were organized. Medical health check-up camps and awareness programmes were organized at different locations.
The International Women's Day was celebrated with active participation of women employees across the organization.
Cadre Development
RVNL continued its long-term strategy of building a strong in-house cadre while maintaining the operational flexibility required for execution of project-based assignments. The Company has progressively enhanced the strength of its regular workforce through absorption and direct recruitment, thereby reducing reliance on deputation in a calibrated manner without compromising project execution capabilities. This balanced manpower strategy will continue to support RVNL's growth trajectory and expanding business portfolio in the years ahead.
5.1 Disclosure under the Sexual Harassment of Women at Workplace (Prevention, Prohibition & Redressal) Act, 2013.
The RVNL Conduct and Discipline Rules are in line with the requirements of the Sexual Harassment of Women at the Workplace (Prevention, Prohibition & Redressal) Act, 2013. An Internal Complaints Committee has been set up in RVNL to redress complaints received regarding sexual harassment. All employees are covered under this policy. The following is a summary of sexual harassment complaints received and disposed off during the financial year: -
i) No. of complaints received: Nil
ii) No. of complaints disposed of: NA
5.2 Right to Information Act
The Company diligently complies with the provisions of the Right to Information Act, ensuring timely responses to all requests received. Appellate Authority, Chief Public Information Officer (CPIO), and Assistant Public
Information Officers (APIOs) have been designated at the Corporate Office, with APIOs also nominated at each PIU. During FY 2025-26, a total of 264 RTI applications were received, of which 250 were disposed of. Seven applications remained under process, while initial action on seven applications was pending at the close of the financial year.
5.3 Rajbhasha (Official Language)
The company has been making concerted efforts to implement the directives of the Government of India on use of Rajbhasha (Official Language). The Rajbhasha Department of the Company has a Part-time Mukhya Rajbhasha Adhikari and Sr. DGM (Rajbhasha) cum Up- Mukhya Rajbhasha Adhikari. All the computers in the Corporate Office have been provided with Unicode compliant software and fonts to facilitate access to common templates in Devnagari. To encourage use of Rajbhasha, total 12 officials who use Rajbhasha in Hindi drafting notes and letters were identified from all the departments and given Late Shankar Dayal Singh Smriti Puraskar amounting to C4,000/- each. A competition on Hindi essay writing, Hindi noting and drafting, Hindi Shabd Gyan and Quiz was organized on the occasion of Hindi Pakhwara in the month of September, 2025. Cash awards of C 1,02,300/- were distributed to 38 successful participants. The Company has also set up a reading room-cum-library room in the Corporate Office with a good collection of books, newspapers and periodicals in Hindi. During 2025-26, 4 meetings of the Rajbhasha Implementation Committee of RVNL were held and promotion of Rajbhasha was discussed and reviewed. During Financial Year 2025-26, Parliamentary Committee (On Official Language) carried out inspection of RVNL's Corporate Office and Committee has expressed satisfaction. During Financial Year 2025-26, Nagar Official Language Implementation Committee, Upkram-2 has provided Rajbhasha Shield to RVNL for organizing Hindi Chitra Varnan Pratiyogita for member offices of Nagar OLIC Upkram-2.
5.4 Presidential Directives:
During the year 2025-26, no presidential directive was received by the Company .
6. Vigilance
The Vigilance Department of RVNL, headed by the Chief Vigilance Officer (CVO), works mainly on a preventive approach to strengthen transparency, accountability, and proper work procedures. Along with investigating complaints from various sources, it also conducts preventive inspections and checks. The findings from these activities are shared with management to enable corrective actions and system improvements, and follow¬ up is done to ensure compliance.
During FY 2025-26, the department focused on clearing pending cases related to the Central Vigilance Commission (CVC) and Chief Technical Examiner Organisation (CTE) by actively coordinating with field units for responses and action taken reports. It also supported one intensive CTE/CVC examination of a work in PIU Chandigarh and responded to observations from earlier inspections.
In total, five CTE-type examinations and two preventive checks were conducted during the year. The department also carried out broader preventive vigilance activities, including surprise inspections, file scrutiny, review of property returns, and examination of audit reports.
DISPOSAL OF COMPLAINTS/INVESTIGATIONS:
The complaints received by Vigilance from time to time were dealt with as per procedure prescribed by CVC & DoPT. During the FY 2025-26, out of (80) complaints (other than PIDPI), 77 complaints were promptly disposed (Filed/ Sent for NA/Registered for Investigation).
A) DISCIPLINARY ACTION:
Minor/Major Penalty dealt in the FY 2025-26.
|
Sl. Penalty
|
Remarks
|
|
No. Minor Major
|
|
01 02 00
|
Two officials on deputation to RVNL, Minor penalty Cases processed by RVNL Vigilance
|
B) VIGILANCE STATUS:
During FY 2025-26 approx. 475 Employees vigilance were processed by RVNL Vigilance as required by HR/RVNL, Railway Board Vigilance, Zonal railways Vigilance etc. All Vigilance status/clearance cases were processed through e-office for prompt disposal.
PREVENTIVE CHECK:
Two preventive check conducted on"procurement of heavy duty commercial networks printers" and "procurement of Antivirus Software "at corporate office RVNL.
C) RECOVERY IN THE FY 2025-26 ON ADVICE OF RVNL VIGILANCE:
Based upon the investigation and inspection of vigilance an amount of rupees C28,331,430/- has been recommended for recovery.
D) VIGILANCE AWARENESS WEEK:
In a move to promote the true spirit of participative vigilance, the Central Vigilance Commission (CVC) issued instructions for a three-month campaign period from 18th August 2025 to 17th November 2025. As per the CVC's guidance, the following preventive vigilance areas were identified as focus points for all Ministries, Departments, and Organizations:
Disposal of pending complaints Disposal of pending cases Capacity building programmes Asset management Digital initiatives
In addition to the above, Rail Vikas Nigam Limited (RVNL) conducted several training and awareness programmes during the campaign period on key themes, including:
Cyber Security and Hygiene Public Procurement Preventive Vigilance Conduct Rules
Ethics, integrity, and attitudinal change "Vigilance - Our Shared Responsibility" Transparency and vigilance in public works
Further, during Vigilance Awareness Week (VAW) 2025, the following activities were also undertaken:
1. Administration of the Integrity Pledge
2. Quiz competitions
3. Nukkad Natak (street plays)
4. Online slogan competitions
5. Webinar on Public Interest Disclosure and Protection of Informers (PIDPI) training programme
. Memorandum of Understanding
The Company secured a rating of "Very Good" by Department of Public Enterprises for the year 2024-25 on the basis of the achievement of the committed targets fixed in the Memorandum of Understanding signed between RVNL and Ministry of Railways.
During FY 2025-26, MoU includes some of the compliance parameters/Main parameters and their compliance status are as follows:
|
S.
No.
|
Compliance Parameter
|
Status of compliance
|
|
1
|
DPE Guidelines on CSR Expenditure
|
Complied
|
|
2
|
Provision in the Companies Act, 2013 (or SEBI (LODR) regulations in case of listed entities) on Corporate Governance:
a. Compositions of board of Directors
b. Board Committees
c. Holding Board and Committees' Meetings
d. Related Party Transactions
e. Disclosures and Transparency
|
Complied
(to the extent the compliance are within the ambit of RVNL.)
|
|
3
|
Onboarding of CPSE on all operational TReDS platforms
|
Complied
|
|
4
|
Timely payments to MSE vendors as prescribed in MSMED Act
|
Complied
|
|
5
|
Procurement of goods and services (as % of total procuremnet), from:
a. MSE overall- 25%
b. SC/ST owned MSEs- 4%
c. Women owned MSEs- 3%
|
Complied
|
|
6
|
Steps and initiative taken for Health and Safety improvement of Human Resourses in CPSEs
|
Complied
|
|
7
|
Targets under PM Internship scheme of MCA
|
Not Applicable
|
|
8
|
Leadership Development Plan
|
Complied
|
|
9
|
Surplus non-core assets (land & building) monetization plan)
|
Complied
Company has not received any target for the financial year 2025-26.
|
The details of DPE MOU 2025-26 target parameter vs achievement alongwith compliance with the DPE OM No. M-03/0006/2024- DPE (MoU) dated 24.03.2026 prescribing mandatory disclosures in the Annual Report of Central Public Sector Enterprises (CPSEs), has been given at Annexure-I.
8.2 Foreign Exchange Earnings and Outgo
The Foreign Exchange outgo during the year in terms of actual outflows as compared to previous year is mentioned below:
9. Risk Management
Your Company has a comprehensive Enterprise Risk Management (ERM) framework in place to proactively identify, assess, and mitigate potential risks. In line with the requirements of the Companies Act, 2013 and SEBI (LODR) Regulations 2015, the Board has constituted a Sub-Committee known as the Risk Management Committee (RMC), which is chaired by the Director (Projects). During FY25-26, the RMC identified following as top risks for the Company:
|
Particulars
|
2025-26
|
2024-25
|
|
Import of Material
|
364.81
|
-
|
|
Import of Capital Goods
|
-
|
-
|
|
Foreign Exchange on foreign travel of Company's officials
|
1.09
|
1.32
|
|
Import of Service
|
3.56
|
3.55
|
|
Rent
|
0.21
|
-
|
|
Purchase of tender
|
-
|
0.04
|
|
Total
|
369.67
|
4.91
|
8. Particulars relating to Conservation of Energy, Technology Absorption and Foreign Exchange Earnings and Outgo etc.
8.1 Conservation of Energy and Technology Absorption
Rail Vikas Nigam Limited is committed to sustainable development through energy efficiency, resource conservation, and environmental protection by promoting renewable energy such as solar installations, energy-efficient LED lighting, and sensor-based systems to reduce power consumption and carbon footprint; implementing water conservation measures including rainwater harvesting, tunnel water utilization, and effluent treatment and reuse; adopting net-zero waste practices and circular economy principles through recycling and eco-friendly infrastructure; undertaking afforestation and ecological restoration through plantation of native species, slope stabilization via turfing, and wildlife conservation to support biodiversity; integrating green building initiatives
through energy-efficient design, sustainable materials, and environmentally conscious planning; supporting community development through livelihood and skill enhancement and local infrastructure improvement; and following sustainable construction practices to minimize environmental impact through efficient resource use and pollution control. Across its projects and offices, the company regularly monitors electricity consumption to improve operational efficiency, with diesel usage largely restricted to emergency backup power requirements, while water consumption and wastewater discharge are systematically tracked to promote responsible use. It also implements environmentally sound waste management practices, including waste segregation at source and disposal of plastic and e-waste through authorized recyclers in compliance with environmental regulations, reflecting its continued commitment to sustainable infrastructure development, regulatory compliance, resource efficiency, and circular economy principles.
1. Compliance & Legal Risks
2. Social Risks
3. Financial Risks
4. Cyber Risks
5. Project related Risks
6. Operational & Safety Risks
The RMC meets regularly and monitors the top risks through reporting of key risk indicators, prepare mitigation plans and monitors their implementation. The risk assessment and the progress of the mitigation measures are reported regularly to the Board of Directors.
10. Corporate Social Responsibility (CSR)
The Company's Corporate Social Responsibility (CSR) Policy is guided by the objective of creating sustainable and inclusive social impact through focused interventions. The key principles of the Policy are as follows:
a) Undertaking CSR initiatives through a project/ programme-based approach to ensure effective implementation and measurable outcomes.
b) Giving priority to the peripheral areas of RVNL's projects, while also addressing the needs of other deserving areas, wherever considered appropriate.
c) Focusing on high-impact sectors such as education and healthcare to promote sustainable community development.
d) Contributing to inclusive socio-economic development with special emphasis on the welfare and empowerment of economically and socially weaker sections of society, including communities residing in aspirational and backward districts of the country.
In compliance with the provisions of Section 135 of the Companies Act, 2013, read with the Companies (Corporate Social Responsibility Policy) Rules, 2014, as amended, and the applicable guidelines issued by the Department of Public Enterprises (DPE), the Company has constituted a Corporate Social Responsibility (CSR) Committee. The details relating to the composition of the CSR Committee, the salient features of the CSR Policy, and the CSR initiatives undertaken by the Company during the Financial Year 2025-26 are provided in **Annexure C**, forming part of this Report.
11. Compliance of provisions of Companies Act, 2013, SEBI (LODR) Regulations, 2015 and Secretarial Standards issued by ICSI
All the provisions of the Companies Act, 2013 and the Rules made thereunder, Secretarial Standards issued by ICSI and SEBI (LODR) Regulations, 2015 to the extent possible and applicable to the Company as well as all relevant notifications thereon issued by the Government of India, are being strictly complied with.
12. Compliance of DPE Guidelines and Policies
All the guidelines and policies including guidelines having financial implications issued by Department of Public Enterprises from time to time are duly complied with by the Company.
13. Compliance of the Public Procurement Policy for Micro and Small Enterprises (MSEs) Order, 2012
The Government of India has notified Public Procurement policy for Micro and Small Enterprises (MSEs) Order, 2012 with effect from 1st April, 2012. As the mandate of the Public Procurement Policy for Micro and Small Enterprises (MSEs) Order 2012, every Central Ministries/ CPSUs is required to set an annual target of minimum 25% procurement of goods & services from MSE Sector. Out of Total annual procurement, a sub target of 4% & 3% should be from MSEs owned by SC/ST and Women entrepreneurs respectively.
Rail Vikas Nigam Limited (RVNL) has taken several steps for effective implementation of MSE Policy. The benefits of waiver of cost of tender documents and deposit of earnest money, prescribed under the policy, are incorporated in the tenders for stores procurement and obtaining services etc.
Shri Ravindra Kumar, ED/HR is working as Nodal as well as the Grievance Officer for seamless implementation of the MSE policy in RVNL. Contact details of said officer is uploaded on RVNL website.
Annual Procurement Plan for purchase from MSEs during the year 2025-26 was made available on RVNL website for information of MSEs and to help them participate in procurement of goods and services.
In the year 2025-26, RVNL procured goods and services amounting to a total of C59.17 crores. Out of this, the total value of goods and services purchased from MSEs (Including MSEs owned by SC/ST and Women entrepreneurs) was to the tune C 17.51 crores i.e. 29.59% of the total procurement. Thus, RVNL has fully complied with the Public Procurement Policy for Micro and Small Enterprises (MSEs) Order, 2012.
As desired, the expenditure incurred by RVNL on under mentioned head of accounts for the period from 01.04.2025 to 31.03.2026 is given below:
|
Particulars
GL Name
|
Details of MSME upto 31.03.2026 FY 2025-26 EIn crore
MSME MSE/SC-
Total ST Tgt 4%
Total
Provisional MSE/ MSE/ MSME of total GL Code Expenditure MSE SC-ST Women provisional
expenditure
|
MSE/
Women Tgt 3% of total provisional expenditure
|
Total MSE Tgt 25% of total provisional expenditure
|
|
Vehicle hiring
|
5206050004
|
5.80
|
1.38
|
2.32
|
-
|
3.70
|
40.10%
|
0.00%
|
63.85%
|
|
Photocopy Exp./Printing & stationary
|
5206110002/
5206110003
|
1.90
|
0.25
|
0.08
|
0.24
|
0.58
|
4.43%
|
12.81%
|
30.54%
|
|
Outsourcing Staff
|
5206120003
|
20.46
|
2.45
|
-
|
0.01
|
2.46
|
0.00%
|
0.05%
|
12.01%
|
|
House Keeping /Security Service
|
5206170003/
5206170004
|
15.29
|
5.32
|
0.09
|
2.49
|
7.91
|
0.61%
|
16.29%
|
51.71%
|
|
Office Equipments
|
1101010001
|
1.16
|
0.05
|
0.01
|
-
|
0.06
|
0.53%
|
0.00%
|
5.08%
|
|
Furniture and Fixtures
|
1101020001
|
3.24
|
0.00
|
-
|
0.01
|
0.01
|
0.00%
|
0.26%
|
0.39%
|
|
EDP Assets
|
1101030001
|
2.30
|
0.08
|
-
|
0.04
|
0.12
|
0.00%
|
1.65%
|
5.24%
|
|
Total (A)
|
|
50.15
|
9.54
|
2.51
|
2.79
|
14.84
|
5.00%
|
5.56%
|
29.59%
|
|
GST calculate on total (A) @18% (Provisional)
|
|
9.03
|
1.72
|
0.45
|
0.50
|
2.67
|
|
|
|
|
Total (A) (including GST)
|
|
59.17
|
11.26
|
2.96
|
3.29
|
17.51
|
5.00%
|
5.56%
|
29.59%
|
d) The Directors have prepared the annual accounts on a going concern basis.
e) The Directors have laid down internal financial controls to be followed by the Company and that such internal financial controls are adequate and were operating effectively.
f) The Directors have devised proper systems to ensure compliance with the provisions of all applicable laws and that such systems were adequate and operating effectively.
16. Directors and Key Managerial Personnel
RVNL being a Government Company, the appointment of directors on its Board are done by the Govt. of India through Administrative Ministry i.e. Ministry of Railways, from time to time.
As on date of this report, the strength of the Board of the Company comprises of Eight (8) Directors, out of which Five (5) are whole-time Directors (including Chairman
and Managing Director), Two (2) Government Nominee Director from Administrative Ministry i.e., Ministry of Railways (MoR) as (Part-time) (official) Directors and One (1) Independent Director as (Part-time) (non-official) Director. Position of six (6) Independent Directors (including one-woman Independent Director) is vacant. However, the composition of the Board of Directors was not in conformity with the provisions of the Companies Act, 2013, SEBI (LODR) Regulations,2015 and DPE Guidelines on Corporate Governance, due to absence of requisite number of Independent Directors including one Woman Independent Director on its Board.
The Company has been requesting Ministry of Railways (MoR), Government of India to appoint requisite number of Independent directors (including woman Independent Director) to ensure the compliance to the provisions of SEBI (LODR) Regulations, 2015 and DPE Guidelines on Corporate Governance. Except the appointment of Independent Directors (including woman Independent Director), the composition of the Board is in compliance with Regulation 17 of SEBI (LODR) Regulations, 2015.
14. Research and Development
Implementation of an Integrated IT Solution for RVNL
RVNL is utilizing a number of IT initiatives to automate the business processes of the organization across employee services, office procedures, project management, and vendor bill processing. Among the latest systems implemented, the following are noteworthy accomplishments:
• RVNL is embarking on the adoption of Data Analytics and Artificial Intelligence (AI) technologies, making its processes more centralized, digitized, and automated.
• RVNL upgraded its Data Centre infrastructure and migrated it to RailTel. With this, the Company's systems are now running on modern and upgraded hardware, resulting in improved performance, reliability, and scalability.
• RVNL continues to enhance its digital ecosystem through the implementation of various IT solutions for improved efficiency, transparency, and governance.
RVNL, being a Navratna Public Sector Enterprise, ensures compliance with the provisions of the Information Technology Act, 2000, and has always remained at the forefront of adopting new technology solutions for the continual improvement of its business processes. With a vision to become a digitally empowered organization for operational excellence and stakeholder value creation, the Company has adopted several innovative technologies in its technology stack.
Various IT projects that are in the pipeline for
implementation include:
• Upgradation of SAP systems from ECC 6.0 to SAP S/4HANA.
• Upgradation of the e-Office platform to enhance digital file management and office automation.
• Revamping of the RVNL Corporate Website to improve user experience, accessibility, and stakeholder engagement.
15. Directors' Responsibility Statement
Pursuant to Section 134(5) of the Companies Act,
2013, the Directors confirm that -
a) In the preparation of the annual accounts, the applicable accounting standards have been followed along with proper explanation relating to material departures;
b) The Directors have selected such accounting policies and applied them consistently and made judgments and estimates that are reasonable and prudent so as to give a true and fair view of the state of affairs of the Company at the end of the financial year and of the profit of the Company for that period;
c) The Directors have taken proper and sufficient care for the maintenance of adequate accounting records in accordance with the provisions of this Act for safeguarding the assets of the Company and for preventing and detecting fraud and other irregularities;
The following Directors held office during the year and till the date of this report-
|
S.
No.
|
Name & DIN of Directors
|
Designation
|
Date of Appointment/ Cessation
|
|
Whole Time Directors/Functional Directors
|
|
1.
|
Mr. Saleem Ahmad
(DIN: 10119432)
|
Chairman and Managing Director
|
From 23.12.2025 onwards
|
|
2.
|
Mr. Sukhmal Chand Jain
(DIN: 07564584)
|
Chairman and Managing Director
|
From 01.09.2025 upto 23.12.2025
|
|
3.
|
Mr. Pradeep Gaur
(DIN: 07243986)
|
Chairman and Managing Director
|
From 01.09.2018 upto 31.08.2025
|
|
4.
|
Mrs. Anupam Ban
(DIN: 07797026)
|
Director (Personnel)
|
From 09.02.2023 onwards
|
|
5.
|
Mr. Mritunjay Pratap Singh
(DIN: 08165734)
|
Director (Operations)
|
From 26.11.2024 onwards
|
|
6.
|
Mr. Abhishek Kumar
(DIN: 10644411)
|
Director (Finance)
|
From 05.06.2025 onwards
|
|
7.
|
Mr. Sanjeeb Kumar
(DIN: 03383641)
|
Director (Finance) & CFO
|
from 06.05.2020 upto 31.05.2025
|
|
8.
|
Mr. Amit Tandon
(DIN: 10167354)
|
Director (Projects)
|
From 02.01.2026 onwards
|
|
9.
|
Mr. Sandeep Jain
(DIN: 09435375)
|
Director (Projects)
|
From 25.11.2024 upto 07.08.2025
|
|
Government Nominee Directors/Part time Official Directors
|
|
10.
|
Mr. Bhartesh Kumar Jain
(DIN: 11508692)
|
Govt. Nominee Director
|
From 28.01.2026 onwards
|
|
11.
|
Mr. Naresh Chandra Karmali
(DIN: 09103211)
|
Govt. Nominee Director
|
From 20.05.2024 onwards
|
|
12.
|
Mr. Prem Sagar Gupta
(DIN: 09329458)
|
Govt. Nominee Director
|
From 06.11.2024 upto 05.01.2026
|
|
Independent Directors/ Part time Non-Official Directors
|
|
13.
|
Mr. Surender Singh
(DIN: 11108145)
|
Independent Director
|
From 15.05.2025 onwards
|
*The Company has received declarations from the Independent Directors confirming that they meet the criteria of independence as prescribed under the Companies Act, 2013 and SEBI (LODR) Regulations, 2015 as amended from time to time.
|
Name
|
Designation
|
Date of change
|
Reasons
|
|
Mr. Amit Tandon
(DIN: 10167354)
|
Director (Projects)
|
02.01.2026
|
Appointment as an Additional Director
|
|
Mr. Saleem Ahmad
(DIN: 10119432)
|
Chairman & Managing Director & Chief Executive Officer
|
23.12.2025
|
Appointment as an Additional Director & Chief Executive Officer
|
|
Mr. Sukhmal Chand Jain
(DIN: 07564584)
|
Chairman & Managing Director
|
23.12.2025
01.09.2025
|
Cessation of office as an Additional Director
Appointment as an Additional Director
|
|
Mr. Pradeep Gaur
(DIN: 07243986)
|
Chairman & Managing Director
|
01.09.2025
|
Cessation of Office due to retirement
|
|
Mr. Sandeep Jain
(DIN: 09435375)
|
Director (Projects)
|
07.08.2025
|
Cessation of Office
|
|
Mr. Abhishek Kumar
(DIN: 10644411)
|
Director (Finance)
|
28.08.2025
05.06.2025
|
Change in designation from Additional Director to Whole-time Director
Appointment as an Additional Director
|
|
Mr. Sanjeeb Kumar
(DIN: 03383641)
|
Director (Finance) & CFO
|
01.06.2025
|
Cessation of Office due to retirement
|
|
Mr. Surender Singh
(DIN: 11108145)
|
Independent Director
|
28.08.2025
15.05.2025
|
Change in designation from Additional Director to Independent Director
Appointment as an Additional Director
|
|
Mr. Chandan Kumar Verma
(DIN: 10298031)
|
ED (Finance) & Chief Financial Officer
|
02.07.2025
|
Appointment as a Chief Financial Officer
|
Woman Director & Independent Woman Director
In terms of the provisions of Section 149 of the Companies Act, 2013 read with the Companies (Appointment and Qualification of Directors) Rules, 2014, a Company shall have at least one-Woman Director on the Board of the Company. Further, as per SEBI (LODR) (Amendment) Regulations, 2018, a Company shall have at least one Independent Women Director. Your Company had no Independent Woman Director on the Board of the Company since 18.09.2020. The Company has requested Ministry of Railways for appointment of Women Independent Directors in order to comply with the requirements under Regulation 17 of SEBI (LODR) Regulations 2015 and Companies Act, 2013.
Annual evaluation by the Board of its own performance and that of its Committees and Individual Directors-
RVNL being a Government Company is exempted vide notification No. F.No.1/2/2014-CL. V dated 5.6.2015 issued by Ministry of Corporate Affairs, to comply with the provisions of Sec 134(3)(e) and Sec 134(3)(p) with respect to Annual evaluation by the Board of its own performance and that of its Committees and Individual Directors. Ministry of Corporate Affairs (MCA) vide General Circular dated 5th June, 2015 has exempted Government Companies from the provisions of Section 178(2) which requires performance evaluation of every director by the Nomination & Remuneration Committee. In case of RVNL, the performance evaluation of Directors is done by the Ministry of Railways as per their laid down procedure.
Appointment/Resignations of Key Managerial Personnel's
The Board of Directors of the Company has designated all the Whole-time Directors, Chief Executive Officer (CEO), Chief Financial Officer (CFO) and Company Secretary as the Key Managerial Personnel (KMP) of the Company; and Chairman & Managing Director (CMD) and Executive Director (Finance) have been designated as CEO and CFO, respectively.
Changes (Appointment/Cessation) in Key Management Personnel's (KMP) during the year and till the date of this report is mentioned in Report on Corporate Governance.
Further, DPE, through our Administrative Ministry (MOR) has started the exercise of performance evaluation/ assessment of non-official (Independent) Directors on the Board of the Company.
Retirement of Directors by Rotation
The Companies Act, 2013 provides that the provisions in respect of retirement of Directors by rotation will not be applicable to Independent Directors. In view of this, no Independent Director is considered to be retiring by rotation; However, all other directors are considered to be retiring by rotation. Accordingly, as per provisions of section 152 of Companies Act, 2013, one third among all other directors namely Smt Anupam Ban, (DIN: 07797026), Director (Personnel) and Shri M.P. Singh, (DIN: 08165734), Director (Operations) being longest in office, are liable to retire by rotation and being eligible, offer himself for re-appointment. The details of Director seeking re-appointment
at the ensuing AGM are contained in the Notice convening the ensuing AGM of the Company.
Meetings of the Board of Directors and Other Committees of the Board and their Composition
Pursuant to the Companies Act, 2013 and Rules framed there under, seven (7) Board Meetings were held in the F.Y. 2025-26. The details of the Meetings are in the Corporate Governance Report forming part of this report. Your Company has Audit Committee, CSR Committee, and other Committees of the Board in place in compliance to Companies Act, 2013 and SEBI (LODR) Regulations. The Composition and scope of the Committees are provided in the report of Corporate Governance, forming part of this report in Annexure-B. Further, there has been no instance where the Board of Directors have not accepted the recommendation of Audit Committee.
A Statement regarding Opinion of the Board with regard to Integrity, Expertise and Experience (including the Proficiency) of the Independent Directors appointed during the year
The Independent directors appointed on the Board of the Company are eminent personalities drawn from fields like Science, Finance, management, i ndustry etc. having wide experience. Upon induction on the Board of the Company, the Independent directors are familiarized with profile of the Company, its business, industry scenario, operations, organizational structure, statutory & regulatory responsibilities through familiarization programme. During the Financial year 2025-26, no Independent Director on the board of Rail Vikas Nigam Limited (RVNL) has resigned from the post of Independent Director. However, the present Independent Director has wide experience in his field and has contributed towards the growth of the Company. In the opinion of the Board, the Independent Director fulfils the conditions specified in the Listing Regulations and are independent of the management.
However, the composition of the Board of Directors was not in conformity with the provisions of the Companies Act, 2013, SEBI LODR Regulations and DPE Guidelines on Corporate Governance, due to absence of requisite number of Independent Directors including Woman Independent Director on its Board. The Company has been requesting Ministry of Railways (MoR), Government of India to appoint requisite number of Independent directors (including woman Independent Director) to ensure the compliance to the provisions of SEBI (LODR) Regulations, 2015 and DPE Guidelines on Corporate Governance. Except the appointment of Independent Directors (including woman Independent Director), the composition of the Board is in compliance with Regulation 17 of SEBI (LODR) Regulations, 2015.
17. Auditors Statutory Auditor
The Comptroller & Auditor General of India has appointed M/s., Gandhi Minocha & Co., Chartered Accountants as Statutory Auditors of the Company for the year ended 31st March, 2026. The Board would like to thank them for their valuable support and guidance during the audit of accounts under review.
Secretarial Auditor
The Board of Directors has appointed M/s Sinha & Srivastava LLP, Practicing Company Secretary to conduct the Secretarial Audit for a priod of 5 years starting from financial year 2025-26. The Secretarial Audit Report is annexed and forms part of this Annual Report in Annexure E.
18. Reporting of Frauds by Auditors
During the year, neither the Statutory Auditor nor the Secretarial Auditor have reported to the Audit Committee under Section 143(2) of the Companies Act, 2013, any instance of fraud committed against the Company by its officers or employees.
19. Comments of Comptroller & Auditor General (C&AG) of India
The Comptroller & Auditor General of India has undertaken supplementary audit on the accounts of the Company for the year ended 31st March, 2026 under Section 139(5) of the Companies Act, 2013. The comments of the C&AG on the Annual Accounts of the Company for the year ended 31st March, 2026 along with management reply, if any, will forms part of this report as and when received.
20. Details of Significant and Material Orders passed by the Regulators or Courts or Tribunals impacting the Going Concern Status and Company's Operations in Future.
No Significant and Material Orders Passed by The Regulators or Courts or Tribunals impacting the Going Concern Status and Company's Operations in Future during the year under Review
21. Particulars of Employees and Related Disclosures
The provisions of Section 134(3) (e) of the Companies Act, 2013 are not applicable to a Government Company. Similarly, Section 197 of the Companies Act, 2013 shall not apply to a Government Company. Consequently, there is no requirement of disclosure of the ratio of the remuneration of each Director to the median employee's remuneration and other such details, including the statement showing the names and other particulars of every employee of the Company, who, if employed throughout/part of the financial year, was in receipt of remuneration in excess of the limits set out in the Rules.
22. Material Changes and Commitments affecting Financial position between the end of the Financial Year and Date of Report
There are no material changes and commitments affecting financial position of the Company which occurred between 01.04.2025 to 31.03.2026 and date of signing of this Report .
23. Cost Records
The Board of Directors has appointed M/s R M Bansal & Co. to conduct the Cost Audit for financial year 2025-26.
24. Difference in amount of the Valuation
There was no such instance of either settlement or loan from Bank or Financial Institution during the year under review.
25. General
Your Directors state that no disclosure or reporting is required in respect of the following matters as there were no transactions on these matters during the year under review:
• Details relating to deposits covered under Chapter V of the Companies Act 2013.
• Issue of equity shares with differential rights as to dividend, voting or otherwise.
• There has been no change in the nature of business of the Company.
26. Corporate Insolvency Resolution Process initiated under the Insolvency and Bankruptcy Code, 2016
The Company has no information to disclose under above.
27. Failure to implement any Corporate Action
The Company has implemented all Corporate Actions successfully within prescribed timelines. Therefore, the Company has nothing to report.
28. Acknowledgements
Your Directors also take this opportunity to gratefully acknowledge the co-operation, guidance, and support in effective management of company's affairs and resources provided by Government of India, in particular Ministry of Railways (MoR), Ministry of Finance, Department of Public Enterprises, various banks, Asian Development Bank, the Zonal Railways, IRFC and our equity partners in Joint Venture SPVs for their continued interest and support to the Company. Your Directors would like to express their thanks for the devotion, commitment and dedication of each and every employee of the Company due to which your Company could face the new challenges and opportunities and create a niche for itself as a major provider of rail infrastructure in the country. Your Directors also acknowledge the support and guidance received from officials of Comptroller & Auditor General of India, Statutory Auditors, and Secretarial Auditors for their suggestions. Last but not the least, the Directors would like to express their deep appreciation and gratitude towards all their predecessors who have been associated with RVNL, for their valuable contribution to the growth and development of the Company in attainment of the Company's aim and goals in all the spheres.
For and on behalf of Board of Directors
Place: New Delhi
Date: 25.07.2026 Sd/-
(Saleem Ahmad)
Chairman & Managing Director DIN: 10119432
|